ACTIVITY-FISH PASSAGE IMPROVEMENT PCSRF
* Miles of Stream Made Accessible
102%
10.19 Actual
10 Planned
Miles
*Number of Blockages/Impediments/Barriers Impeding Passage
150%
3 Actual
2 Planned
Number
ACTIVITY-FISH SCREENING PROJECT PCSRF
Number Of Fish Screens Installed | Not entered |
Number Of Fish Screens Replaced Or Modified | 01 Number |
ACTIVITY-INSTREAM FLOW PROJECT PCSRF
Cfs (Cubic Feet Per Second) Of Water Conserved
150%
4.5 Actual
3 Planned
Cu Feet per Sec
Change In Water Flow
92%
10.57 Actual
11.5 Planned
Cu Feet per Sec
Miles Of Stream 'Protected' For Adequate Flow
373%
17.15 Actual
4.6 Planned
Miles
Cfs (Cubic Feet Per Second) Of Water Purchased/Leased | 00.25 Cu Feet per Sec |
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Miles of Streambank Stabilized
100%
0.28 Actual
0.28 Planned
Miles
Number of structures placed in channel
550%
55 Actual
10 Planned
Number
Total Miles Of Instream Habitat Treated
32%
1.68 Actual
5.3 Planned
Miles
Acres Of Off-Channel/Floodplain Connected Or Added | 02.35 Acres | 10/31/2013 - 10/1/2015 |
Cubic Yards of spawning gravel placed | Not entered |
Miles of Off-Channel Stream Created | 00.59 Miles |
Miles of Stream Treated with spawning gravel placement | Not entered |
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated
203%
18.68 Actual
9.2 Planned
Acres
* Total Riparian Miles Streambank Treated
641%
6.73 Actual
1.05 Planned
Miles
Acres Planted in riparian
626%
23.18 Actual
3.7 Planned
Acres
Acres of riparian treated for plant removal/control | 09.86 Acres |
Miles of Fence Along Stream | 00.88 Miles |
ACTIVITY-WETLAND PROJECT PCSRF
Total Acres Of Wetland Area Treated | Not entered |