Entiat Sub-basin
#Level 1 #Level 1
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor
Status Active
Schedule Start Date: 5/1/2000 End Date: 12/31/2022
Priority 1
Category Category: Habitat Protection & Restoration
DESCRIPTION
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PROJECT CONTACT
PHOTOS

 
View project on a larger map

Related Projects

ACTIVITY-FISH PASSAGE IMPROVEMENT PCSRF
* Miles of Stream Made Accessible
55%
5.49 Actual
10 Planned
Miles
*Number of Blockages/Impediments/Barriers Impeding Passage
150%
3 Actual
2 Planned
Number
ACTIVITY-FISH SCREENING PROJECT PCSRF
Number Of Fish Screens InstalledNot entered
Number Of Fish Screens Replaced Or Modified 01 Number
ACTIVITY-INSTREAM FLOW PROJECT PCSRF
Cfs (Cubic Feet Per Second) Of Water Conserved
150%
4.5 Actual
3 Planned
Cu Feet per Sec
Change In Water Flow
92%
10.57 Actual
11.5 Planned
Cu Feet per Sec
Miles Of Stream 'Protected' For Adequate Flow
373%
17.15 Actual
4.6 Planned
Miles
Cfs (Cubic Feet Per Second) Of Water Purchased/Leased 00.25 Cu Feet per Sec
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Acres Of Off-Channel/Floodplain Connected Or Added
289%
17.35 Actual
6 Planned
Acres
Miles of Off-Channel Stream Created
236%
0.59 Actual
0.25 Planned
Miles
Miles of Streambank Stabilized
171%
0.48 Actual
0.28 Planned
Miles
Number of structures placed in channel
411%
74 Actual
18 Planned
Number
Total Miles Of Instream Habitat Treated
56%
3.28 Actual
5.9 Planned
Miles
Cubic Yards of spawning gravel placedNot entered
Miles of Stream Treated with spawning gravel placementNot entered
ACTIVITY-REAL PROPERTY ACQUISITION PCSRF
Acres Of Land, Wetland Or Estuarine Area Conserved By Acquisition Or Lease
538%
626.15 Actual
116.39 Planned
Acres
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated
342%
36.63 Actual
10.7 Planned
Acres
* Total Riparian Miles Streambank Treated
591%
7.98 Actual
1.35 Planned
Miles
Acres Planted in riparian
671%
34.88 Actual
5.2 Planned
Acres
Acres of riparian treated for plant removal/control 09.86 Acres
Miles of Fence Along Stream 00.88 Miles
ACTIVITY-WETLAND PROJECT PCSRF
Total Acres Of Wetland Area TreatedNot entered