Entiat PUD Canal System Conversion Project
#07-1788 #07-1788
 Entiat Sub-basin Lower Entiat Entiat PUD Canal System Conversion Project
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Cascadia Conservation District
Status Completed
Schedule Start Date: 12/13/2007 End Date: 8/30/2012
Category Category: Restoration
Project Photo
DESCRIPTION
Decommissioning the leaking and inefficient PUD irrigation system pipeline and delivery system and converting existing irrigation water users to wells will create water savings of 2.7 – 3.3 cfs between RM 3.45 and 1.7 (pipeline intake and outfall) and improve lower Entiat River instream flow conditions. To create improved off-channel habitat conditions year-round targeted at benefiting adult and juvenile steelhead (spring Chinook juveniles may also benefit), flows in the canal will be reduced 8-9 cfs, resulting in a savings of 8-9 cfs in the mainstem in the 0.15 mile between the canal diversion and outfall. The Entiat PUD Canal System Conversion Project is located in the lower portion (RM 0.0- RM16.2; Category 2 subwatershed) of the Entiat River in Chelan County. The canal runs along the Entiat River in T25 R20 Sec13 and T25 R21 Sec18 in Chelan County. The canal irrigation water canal diversion and return outfall are located approximately River Mile 3.45 miles and RM 1.49 miles, respectively. The Entiat PUD Canal System Conversion project will address water quantity and water quality issues, particularly late-season instream flows, help moderate stream temperature extremes and improve water quality in the lower Entiat, and facilitate salmonid access to spawning and rearing habitats. In addition, it complements the suite of habitat improvement actions implemented instream adjacent to and within the canal last year as part of Phase 1 of the Bridge-to-Bridge project.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/17/2007Cascadia Conservation DistrictMatch$212,760.00
Requested09/17/2007Recreation and Conservation Office (RCO)Salmon State Projects$283,824.00
Allocated06/19/2012Cascadia Conservation DistrictMatch$188,405.72
Allocated06/19/2012Recreation and Conservation Office (RCO)Salmon Federal Projects$251,307.75
Spent07/12/2011Recreation and Conservation Office (RCO)Salmon State Projects-$0.00
Spent06/19/2012Cascadia Conservation DistrictMatch-$188,405.72
Spent06/19/2012Recreation and Conservation Office (RCO)Salmon Federal Projects-$251,307.75
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$496,584.00 $496,584.00 $439,713.47 $439,713.47 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Entiat River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
County:Chelan
HUC12:Mills Creek-Entiat River (170200100209)
HUC8:Upper Columbia-Entiat (17020010)
Lead Entity Area:Upper Columbia
Legislative District:12
Salmon Recovery Regions:Upper Columbia River
Sections:13
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Entiat River, Threatened
Township:T25NR20E
Upper Columbia Assesment Unit:Entiat River-Mills Creek
Watershed Administrative Unit:Lower Entiat
WRIA:Entiat
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.75mi1.75mi
Fish Screening Project    
Quantity Of Water Protected By Screens (acre feet per year) (C.1.b)
0.00acre-ft/yr
 Fish screens installed (C.1.c.1)    
Change in water flow (fish screen project)(cu feet)
0.00cfs
Number Of Fish Screens Installed (C.1.c.2)
0.00
The Flow Rate Of Screened Water (C.1.c.3)
0.00cfs
Instream Flow Project    
Change In Water Flow (C.3.c)
9.00cfs7.00cfs
Miles Of Stream 'Protected' For Adequate Flow (C.3.b)
1.75mi
 Irrigation practice improvement (C.3.e.1)    
Acre Feet Of Water Conserved (C.3.e.2)
0.00acre-feet
Cfs (Cubic Feet Per Second) Of Water Conserved (C.3.e.3)
0.00cfs
ADDITIONAL INFORMATION