| Organization | Upper Columbia Salmon Recovery Board Lead Entity |
| Sponsor | Cascadia Conservation District |
| Status | Completed |
| Schedule | Start Date: 1/15/2009 End Date: 2/14/2012 |
| Category | Category: Restoration |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|---|---|---|---|---|
| Requested | 07/13/2009 | Recreation and Conservation Office (RCO) | Salmon State Projects | $42,625.00 | |
| Requested | 07/13/2009 | Cascadia Conservation District | Match | $43,378.00 | |
| Allocated | 02/03/2012 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $18,848.15 | |
| Allocated | 02/03/2012 | Cascadia Conservation District | Match | $31,273.85 | |
| Spent | 02/03/2012 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | -$18,848.15 | |
| Spent | 02/03/2012 | Cascadia Conservation District | Match | -$31,273.85 |
| Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
| $22,583.00 | $86,003.00 | $50,122.00 | $50,122.00 | $0.00 |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|
| Other Funding Totals | Requested | Allocated | Spent | Balance | |
| Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
| Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Entiat River, Endangered |
| Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
| Coho-Pop (ESU): | Coho-Interior Columbia, Not Warranted |
| County: | Chelan |
| HUC12: | Mills Creek-Entiat River (170200100209) |
| HUC8: | Upper Columbia-Entiat (17020010) |
| Lead Entity Area: | Upper Columbia River |
| Legislative District: | 12 |
| Salmon Recovery Regions: | Upper Columbia River |
| Sections: | 18 |
| Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Entiat River, Threatened |
| Township: | T25NR21E |
| Upper Columbia Assesment Unit: | Entiat River-Mills Creek |
| Watershed Administrative Unit: | Lower Entiat |
| WRIA: | Entiat |
| APPLICATION | FINAL | ||||
| RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.00 | mi | 0.80 | mi | |
| Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.10 | mi | |||
| Channel structure placement (C.4.d.1) | |||||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.05 | mi | |||
Number of structures placed in channel (C.4.d.7) | 10.00 | ||||
Pools Created through channel structure placement (C.4.d.5) | 6.00 | ||||
| Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 5.50 | acres | 5.50 | acres | |
*Total Riparian Miles Streambank Treated (C.5.b.1) | 0.80 | mi | 0.80 | mi | |
| Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | 5.50 | acres | |||
| Riparian Plant removal / control (C.5.h.1) | |||||
Acres of riparian treated for plant removal/control (C.5.h.3) | 0.00 | acres | 0.00 | acres | |