DESCRIPTION
Bainbridge Island shoreline and streams
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PROJECT CONTACT
GRANT WRITER
LIKELY PROJECT SPONSOR
GRANT MANAGER
LEAD ENTITY COORDINATOR
SECONDARY SPONSOR
PHOTOS

 
View project on a larger map

Related Projects

ACTIVITY-ESTUARINE / NEARSHORE PROJECT PCSRF
* Total Amount of Estuarine / Nearshore Acres Treated
86%
5.25 Actual
6.1 Planned
Acres
Acres of Estuarine planting or native plant establishment
100%
1.6 Actual
1.6 Planned
Acres
Acres of Estuary Created
80%
0.4 Actual
0.5 Planned
Acres
Miles of Shoreline Treated for armor modification/removal
314%
1.1 Actual
0.35 Planned
Miles
Miles of Shoreline Treated for beach nourishment
500%
0.05 Actual
0.01 Planned
Miles
ACTIVITY-FISH SCREENING PROJECT PCSRF
Number Of Fish Screens Installed
100%
1 Actual
1 Planned
Number
ACTIVITY-REAL PROPERTY ACQUISITION PCSRF
Acres Of Land, Wetland Or Estuarine Area Conserved By Acquisition Or Lease
199%
152.36 Actual
76.49 Planned
Acres
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated
103%
7.9 Actual
7.7 Planned
Acres
* Total Riparian Miles Streambank Treated
0%
0 Actual
0.25 Planned
Miles
Acres of riparian treated for plant removal/control
103%
7.9 Actual
7.7 Planned
Acres
Acres Planted in riparian
100%
2.7 Actual
2.7 Planned
Acres
Miles of streambank treated for plant removal/control
100%
0.1 Actual
0.1 Planned
Miles
ACTIVITY-UPLAND HABITAT AND SEDIMENT PROJECT PCSRF
Acres of Upland Habitat Area Treated
300%
0.3 Actual
0.1 Planned
Acres
Total Miles of Road Treated
1600%
0.16 Actual
0.01 Planned
Miles
ASSESSMENTS
assessment report completion 01 Each
BULKHEAD REMOVAL
bulkhead removal 1,720 Feet
DESIGN PLANS FOR CONSTRUCTION
design or plan was completed as funded 02 Each