Strawberry Plant Restoration Construction 2008
#08-1971 #08-1971
 North Kitsap projects Bainbridge Island Strawberry Plant Restoration Construction 2008
Organization West Sound Partners for Ecosystem Recovery
Sponsor City of Bainbridge Island
Status Completed
Schedule Start Date: 12/12/2008 End Date: 6/27/2011
Category Category: Restoration
Project Photo
DESCRIPTION
The overall project will restore approximately 1.5 acres of stream mouth, intertidal, and fringe marsh habitat as well as 0.5 acres of riparian habitat. The Strawberry Plant property is one of the most significant opportunities to restore lost habitat in Eagle Harbor and will benefit salmon, other fish, shellfish, birds, and other wildlife. The property is a public park currently owned by the City of Bainbridge Island and the ownership will eventual be transferred to the Bainbridge Island Metropolitan Park and Recreation District and upland park planning and development will be completed. Eagle Harbor has suffered significant habitat impacts, including the historic filling of two fairly large subestuary marsh/lagoon habitats in the outer harbor that can never be restored due to Superfund reclamation. The project site is located near a recently restored salmon stream (almost 1 mile of habitat opened to chum, cutthroat, coho), 7 small stream subestuaries, 7 recently completed or in-progress nearshore restoration projects, and an aquatic conservancy area (see nearby habitat map). The project included restoration of intertidal habitat, marsh, and marine vegetation and included removing creosote piles, concrete bulkhead and rip rap, debris and fill material, and reducing impervious surfaces in the shoreline area; establishing a natural shoreline and stream mouth; and creating a salt marsh along the shoreline and stream mouth. Public recreational components related to the restoration project included establishing pedestrian public viewing and direct water access points and a non-motorized boating access area.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/08/2008Recreation and Conservation Office (RCO)Salmon State Projects$252,395.00
Requested09/08/2008City of Bainbridge IslandMatch$373,443.00
Allocated11/29/2010Recreation and Conservation Office (RCO)Salmon Federal Projects$298,776.00
Allocated11/29/2010City of Bainbridge IslandMatch$373,443.00
Spent06/27/2011Recreation and Conservation Office (RCO)Salmon Federal Projects-$298,776.00
Spent06/27/2011City of Bainbridge IslandMatch-$373,443.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$672,219.00 $625,838.00 $672,219.00 $672,219.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Bainbridge Island
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Kitsap
HUC12:Bainbridge Island (171100190404)
HUC8:Puget Sound (17110019)
Lead Entity Area:West Sound
Legislative District:23
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:North Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:27
Steelhead-Pop (ESU):Steelhead-Puget Sound, East Kitsap Peninsula Tributaries, Threatened
Township:T25NR02E
Watershed Administrative Unit:Bainbridge Island
WRIA:Kitsap
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.10mi0.10mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
1.50acres1.50acres
 Beach nourishment (C.9.l.1)    
Acres Treated for beach nourishment (C.9.l.4)
0.60acres
Cubic Yards Of Beach Substrate Placed (C.9.l.2)
132.00cubic yds
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
0.04mi
 Creation of new estuarine area (C.9.q.1)    
Acres of Estuary Created (C.9.q.2)
0.50acres0.40acres
 Debris removal (C.9.n.1)    
Acres Treated for debris removal (C.9.n.2)
1.20acres
 Estuarine plant removal / control (C.9.j.1)    
Acres of Estuary Treated for plant removal/control (C.9.j.3)
3.10acres2.00acres
 Exclusion devices (C.9.p.1)    
Acres Treated with exclusion devices (C.9.p.2)
0.10acres
 Regrading of slope (C.9.i.1)    
Acres of Estuary Treated through slope regrading (C.9.i.2)
0.50acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
1.00acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.10mi
Upland Habitat And Sediment Project    
Acres of Upland Habitat Area Treated (C.6.b.1)
0.10acres
Miles of Road Treated (C.6.b.2)
0.01mi
 Road drainage system improvements and reconstruction (C.6.c.1)    
Average width of road treated for drainage improvements and reconstruction (C.6.c.3)
0.00yd
Miles of Road Treated for drainage improvements and reconstruction (C.6.c.2)
0.00mi
ADDITIONAL INFORMATION