Royal Arch Reach Acquisitions
#09-1578 #09-1578
Organization Lake Washington/Cedar/Sammamish Watershed (WRIA 8) Lead Entity
Sponsor Seattle Public Utilities
Status Completed
Schedule Start Date: 12/10/2009 End Date: 3/14/2012
Category Category: Acquisition
DESCRIPTION
This project acquired two properties, four parcels, totaling 3.75 acres, to protect and later restore Chinook salmon habitat at river mile 13.19 to 14.19 on the Cedar River in WRIA 8 (King County). Under its Cedar River Watershed Habitat Conservation Plan (HCP) Seattle Public Utilities is engaged in land acquisition for salmon habitat protection and restoration in the lower Cedar River, below its municipal watershed ownership boundary at the Landsburg Diversion Dam. After the December 2008 flood, several property owners in the Royal Arch Reach (River Mile13.19 to 14.19) expressed interest in selling their property. To date, SPU has acquired 7.03 acres of riverfront property in this reach and has an additional 1.21 acres under contract. The Royal Arch Reach provides promising habitat restoration opportunities to benefit Chinook salmon. For example, a geomorphic feature on one targeted parcel likely marks an historic river channel, providing a potential side channel development opportunity for Chinook spawning and rearing and high flow refuge for juveniles. This reach was inundated during the December 2008 flood, demonstrating the river’s inclination to migrate outside its current main channel location. Acquisition of these parcels would provide restoration opportunities that would enable the river to migrate in the floodplain, thereby increasing habitat complexity, including off-channel features, large wood, pools and riffles, and improved gravel recruitment.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/31/2009Seattle Public UtilitiesMatch$88,000.00
Requested08/31/2009Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$500,000.00
Allocated12/10/2009Seattle Public UtilitiesMatch$88,250.00
Allocated12/10/2009Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$500,000.00
Spent03/14/2012Seattle Public UtilitiesMatch-$88,250.00
Spent03/14/2012Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$500,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
Not entered $588,000.00 $588,250.00 $588,250.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Cedar River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Hobart
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:King
HUC12:Madsen Creek-Cedar River (171100120107)
HUC8:Lake Washington (17110012)
Lead Entity Area:Lake Washington/Cedar/Sammamish Watershed (WRIA 8)
Legislative District:05
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:04
Sections:09
Steelhead-Pop (ESU):Steelhead-Puget Sound, Cedar River, Threatened
Township:T22NR06E
Watershed Administrative Unit:Lower Cedar River
WRIA:Cedar - Sammamish
View project on a larger map

Related Projects

  APPLICATION FINAL 
ACQUISTION METRICS
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
0.11mi
 Land    
Acres by Acreage Type (fee simple)
Riparian
39.06
Total
39.06
acres
Riparian
3.75
Total
3.75
acres
 
WORKSITE METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.00mi0.25mi