Royal Arch Reach Floodplain Reconnect (Ph1) Design
#CR-14-15-RB2 #CR-14-15-RB2
 Tier 1 Cedar River Royal Arch Reach Floodplain Reconnect (Ph1) Design
Organization Lake Washington/Cedar/Sammamish Watershed (WRIA 8) Lead Entity
Sponsor Seattle Public Utilities
Status Completed
Schedule Start Date: 12/13/2019 End Date: 5/5/2023
Category Category: Planning
DESCRIPTION
90% design was completed in 4Q 2022 and all permitting for construction was completed or near completed by all issuing authorities (finalized in 1Q 2023), including all cultural resources permitting, consultations, and approved Incidental Discover Plan (IDP) The project design meets all of the restoration design objectives enumerated in the proposal.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested05/01/2019Seattle Public UtilitiesMatch$74,835.00
Requested05/01/2019Recreation and Conservation Office (RCO)Salmon State Projects$424,065.00
Allocated05/23/2023Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$42,279.00
Allocated05/23/2023Seattle Public UtilitiesMatch$115,962.00
Allocated05/23/2023Recreation and Conservation Office (RCO)Salmon Federal Projects$424,065.00
Spent05/05/2023Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$42,279.00
Spent05/05/2023Seattle Public UtilitiesMatch-$115,962.00
Spent05/05/2023Recreation and Conservation Office (RCO)Salmon Federal Projects-$424,065.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$3,000,000.00 $498,900.00 $582,306.00 $582,306.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Cedar River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Hobart
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:King
HUC12:Madsen Creek-Cedar River (171100120107)
HUC8:Lake Washington (17110012)
Lead Entity Area:Lake Washington/Cedar/Sammamish Watershed (WRIA 8)
Legislative District:05
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:09
Steelhead-Pop (ESU):Steelhead-Puget Sound, Cedar River, Threatened
Township:T22NR06E
Watershed Administrative Unit:Lower Cedar River
WRIA:Cedar - Sammamish
View project on a larger map

Related Projects

  APPLICATION FINAL 
PLANNING METRICS
Area Encompassed (acres) (B.0.b.1)
9.00acres11.60acres
Miles of Stream and/or Shoreline Affected (B.0.b.2)
0.47mi0.78mi