Peshastin Creek
#Level 2 #Level 2
 Wenatchee Sub-basin Peshastin Creek
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor
Status Active
Schedule Start Date: 1/1/1987 End Date: 1/1/2025
Priority 1
Category Category: 
DESCRIPTION
Show more  ↓
FUNDING
Proposed Cost $11,255,027.17
Requested Funds $0
Allocated Funds $0
Spent Funds $0
Balance $0
FUNDING SOURCES
PROJECT CONTACT
PHOTOS

 
View project on a larger map

Related Projects

ACTIVITY-FISH PASSAGE IMPROVEMENT PCSRF
* Miles of Stream Made Accessible
113%
19.4 Actual
17.2 Planned
Miles
*Number of Blockages/Impediments/Barriers Impeding Passage
1000%
10 Actual
1 Planned
Number
Number of bridges
0%
0 Actual
1 Planned
Number
ACTIVITY-FISH SCREENING PROJECT PCSRF
Number Of Fish Screens InstalledNot entered
ACTIVITY-INSTREAM FLOW PROJECT PCSRF
Cfs (Cubic Feet Per Second) Of Water Conserved
200%
2 Actual
1 Planned
Cu Feet per Sec
Change In Water Flow
217%
2.6 Actual
1.2 Planned
Cu Feet per Sec
Miles Of Stream 'Protected' For Adequate Flow
480%
4.8 Actual
1 Planned
Miles
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Acres Of Off-Channel/Floodplain Connected Or Added 37.5 Acres
Miles of Off-Channel Stream Created 00.15 Miles
Miles of Streambank Stabilized 00.15 Miles
Number of structures placed in channel 06 Number
Total Miles Of Instream Habitat Treated 01.25 Miles