CCNRD Peshastin Irrigation Pipeline Schedule A
#SRP-08-1791 #SRP-08-1791
 Wenatchee Sub-basin Peshastin Creek CCNRD Peshastin Irrigation Pipeline Schedule A
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Chelan County Natural Resources Department
Status Completed
Schedule Start Date: 1/6/2008 End Date: 12/30/2011
Priority 1
Category Category: Restoration
Project Photo
DESCRIPTION

In 2010, approximately 6000 ft of Peshastin Irrigation District Canal was converted from an open canal to a closed pipeline. The construction of this pipeline will eliminate seepage in that reach. The upstream end of the proposed pipeline ties into a pipeline constructed in 2005 by Peshastin Irrigation District. Once completed, with Schedule B, this project will save a conservatively estimated 1.2 cfs which is a significant amount during low flows in Peshastin Creek that can go down to 3.5 cfs in late summer. This water savings will reduce diversions from Peshastin Creek and increase instream flow for fish passage.

Phase 2 of this project was completed in 2011. See the page for Peshastin Irrigation Pipeline Schedule B

http://waconnect.paladinpanoramic.com/Project/290/16093

Show more  ↓
FUNDING
Proposed Cost $906,622
Requested Funds $0
Allocated Funds $0
Spent Funds $0
Balance $0
FUNDING SOURCES
PROJECT CONTACT
LAND OWNER
PARTNER
PROJECT MANAGER
SPONSOR
PHOTOS

 
LOCATION
Sections:06
Legislative District:12
HUC12:Brender Creek-Mission Creek (170200110604)
County:Chelan
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Wenatchee River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Wenatchee River, Threatened
Township:T23NR19E
Lead Entity Area:Upper Columbia
Salmon Recovery Regions:Upper Columbia River
WRIA:Wenatchee
HUC8:Wenatchee (17020011)
View project on a larger map

Related Projects

ACTIVITY-INSTREAM FLOW PROJECT PCSRF
Cfs (Cubic Feet Per Second) Of Water Conserved 00.6 Cu Feet per Sec
Miles Of Stream 'Protected' For Adequate Flow 02.4 Miles
PROJECT SCHEDULE
2007 Design by Reclamation
2007 Permitting
2007 Survey
2008 Construction