Organization | Upper Columbia Salmon Recovery Board Lead Entity |
Sponsor | Confederated Tribes and Bands of the Yakama Nation (YN) |
Status | Completed |
Schedule | Start Date: 3/31/2011 End Date: 10/31/2012 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Allocated | 11/14/2017 | Chelan County Natural Resources Department | $130,000.00 | ||
Allocated | 11/14/2017 | US Bureau of Reclamation | $75,000.00 | ||
Allocated | 11/14/2017 | Confederated Tribes and Bands of the Yakama Nation (YN) | $25,000.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$130,000.00 | $0.00 | $230,000.00 | $0.00 | $230,000.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Wenatchee River, Endangered |
Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
County: | Chelan |
HUC12: | Lower Peshastin Creek (170200110503) |
HUC8: | Wenatchee (17020011) |
Lead Entity Area: | Upper Columbia |
Legislative District: | 12 |
Salmon Recovery Regions: | Upper Columbia River |
Sections: | 29 |
Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Wenatchee River, Threatened |
Township: | T24NR18E |
Upper Columbia Assesment Unit: | Lower Peshastin Creek |
Watershed Administrative Unit: | Mt Stuart |
WRIA: | Wenatchee |
Project Plans & Materials Specifications for Peshastin Fishway |