| Organization | Upper Columbia Salmon Recovery Board Lead Entity |
| Sponsor | Confederated Tribes and Bands of the Yakama Nation (YN) |
| Status | Completed |
| Schedule | Start Date: 3/31/2011 End Date: 10/31/2012 |
| Category | Category: Restoration |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|---|---|---|---|---|
| Allocated | 11/14/2017 | Chelan County Natural Resources Department | $130,000.00 | ||
| Allocated | 11/14/2017 | US Bureau of Reclamation | $75,000.00 | ||
| Allocated | 11/14/2017 | Confederated Tribes and Bands of the Yakama Nation (YN) | $25,000.00 |
| Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
| $130,000.00 | $0.00 | $230,000.00 | $0.00 | $230,000.00 |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|
| Other Funding Totals | Requested | Allocated | Spent | Balance | |
| Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
| Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Wenatchee River, Endangered |
| Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
| County: | Chelan |
| HUC12: | Lower Peshastin Creek (170200110503) |
| HUC8: | Wenatchee (17020011) |
| Lead Entity Area: | Upper Columbia River |
| Legislative District: | 12 |
| Salmon Recovery Regions: | Upper Columbia River |
| Sections: | 29 |
| Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Wenatchee River, Threatened |
| Township: | T24NR18E |
| Upper Columbia Assesment Unit: | Lower Peshastin Creek |
| Watershed Administrative Unit: | Mt Stuart |
| WRIA: | Wenatchee |
| APPLICATION | FINAL | ||||
| RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | |||||
| Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 0.10 | mi | 0.10 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | 1.00 | |||
| Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.15 | mi | 0.15 | mi | |
| Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.15 | mi | 0.15 | mi | |
| Project Plans & Materials Specifications for Peshastin Fishway |