Ruby Creek Culvert at Sidney Rd Port Orchard
#(RC4) #(RC4)
Organization West Sound Partners for Ecosystem Recovery
Sponsor City of Port Orchard
Status Proposed
Schedule Start Date: 1/15/2025 End Date: 4/30/2028
Category Category: Restoration
DESCRIPTION
The City of Port Orchard will use this grant to fund the removal of the Ruby Creek Barrier at Sidney Rd. to improve fish passage within the creek. The barrier is located on Sidney Rd. approximately 3000 ft north of the intersection of Sedgwick Rd. and Sidney Rd. (-122.65304 x 47.50117). This is the lowest and most significant barrier on Ruby Creek before it merges with Blackjack Creek, substantially blocking fish migration from Blackjack upstream to Ruby. Funding this project will help to restore stream connectivity between Ruby Creek and Blackjack Creek, improving passage of populations of Endangered Species Act listed East Kitsap DIP Steelhead, Coho, Chinook, Chum and Cutthroat that are present in both streams. The primary habitat that will be restored is in-stream habitat and riparian habitat creating accessibility for fish to approximately 1,102 square meters of spawning habitat and 44,382 square meters of rearing habitat. This culvert has been rated by WDFW with a PI total of 37.86. This barrier removal will improve habitat connectivity and increase fecundity of existing fish populations by removing  barriers and restoring natural vegetation and processes to Ruby Creek, promoting angling and wildlife viewing opportunities. Several other barrier removals have been conducted or are scheduled upstream and downstream of the Sidney Rd. barrier, leaving this culvert the last limiting barrier for fish migration on Ruby Creek. Removing this barrier opens 0.81 miles of stream.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested01/13/2022City of Port OrchardMatch$326,973.00
Requested01/13/2022Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board$1,852,842.00
AllocatedCity of Port OrchardMatch$326,973.00
AllocatedRecreation and Conservation Office (RCO)BA Fish Barrier Removal Board$1,852,842.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
Not entered $2,179,815.00 $2,179,815.00 $0.00 $2,179,815.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Port Orchard
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Kitsap
HUC12:Blackjack Creek-Frontal Port Orchard (171100190704)
HUC8:Puget Sound (17110019)
Lead Entity Area:West Sound
Legislative District:26
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:North Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:11
Steelhead-Pop (ESU):Steelhead-Puget Sound, East Kitsap Peninsula Tributaries, Threatened
Township:T23NR01E
Watershed Administrative Unit:S Sinclair Inlet
WRIA:Kitsap
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
0.81mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
Miles Of Stream Made Accessible (FBRB)
0.81mi
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
5.50mi
Number of culverts (C.2.f.2)
1.00