Klickitat Floodplain Restoration Phase 4
#12-1644 #12-1644
 WRIA 30 - Klickitat Basin Klickitat Mainstem Klickitat Floodplain Restoration Phase 4
Organization Klickitat Lead Entity
Sponsor Columbia Land Trust
Status Completed
Schedule Start Date: 12/6/2012 End Date: 9/3/2015
Category Category: Restoration
DESCRIPTION
The Klickitat Floodplain Restoration Phase 4 project enhanced and restored riparian and floodplain habitat between river mile 22.52 and 23.85 of the Klickitat River. The project addressed limiting habitat features and processes identified in the 2012 Klickitat Lead Entity Salmon Recovery Strategy for this reach by fill removal and pull back of floodplain road to restore connectivity, establish river contact with bedrock, and soften channel boundary along 1.33 miles of road which included riparian plant removal and control and fish passage barrier removal. Treated areas were revegetated with native species to enhance riparian vegetation and improve near-bank and off-channel habitat conditions for steelhead and salmon. This portion of the river has the greatest habitat complexity of any reach in the lower Klickitat River and provides critical spawning, migration and rearing habitat for winter and summer steelhead (ESA-Threatened), spring and fall chinook salmon, and coho salmon. The project is encompassed by the "Lower Klickitat Mainstem: Little Klickitat to Leidl Bridge" reach, which is in the top tier ("A" priority) of the geographic priorities identified in the 2012 Klickitat Lead Entity Salmon Recovery Strategy. This reach provides a high proportion of basinwide spawning habitat for all three species, accounting for roughly 30%, 51%, and 38% of the annually observed spawning for steelhead, fall chinook, and coho respectively. Phase 4 continued the SRFB funded work beginning in 2004 with the acquisition of the Haul Road and three phases of restoration projects since.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/24/2012Columbia Land TrustMatch$99,397.00
Requested08/24/2012Recreation and Conservation Office (RCO)Salmon State Projects$527,000.00
Allocated09/03/2015Columbia Land TrustMatch$99,392.73
Allocated09/03/2015Recreation and Conservation Office (RCO)Salmon Federal Projects$526,977.37
Spent09/03/2015Columbia Land TrustMatch-$99,392.73
Spent09/03/2015Recreation and Conservation Office (RCO)Salmon Federal Projects-$526,977.37
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$626,397.00 $626,397.00 $626,370.10 $626,370.10 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Middle Columbia River Spring, Not Warranted
Chum-Pop (ESU):Chum-Columbia River, Upper Gorge Tributaries, Outside anadromous area
County:Klickitat
HUC12:Beeks Canyon-Klickitat River (170701060402)
HUC8:Klickitat (17070106)
Lead Entity Area:Klickitat County
Legislative District:14
Salmon Recovery Regions:Middle Columbia River
Sections:06
Sections:31
Steelhead-Pop (ESU):Steelhead-Middle Columbia River, Klickitat River, Threatened
Township:T04NR14E
Township:T05NR14E
Watershed Administrative Unit:Dead Canyon
WRIA:Klickitat
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.32mi1.33mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
0.19mi0.43mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.19mi0.43mi
Number of road-crossings (C.2.i.2)
1.001.00
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.88mi1.10mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
7.60acres8.60acres
Instream Pools Created/Added (C.4.c.6)
0.002.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.00mi0.47mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.00mi1.10mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
21.50acres16.10acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
4.29mi1.33mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
7.60acres7.60acres
Miles of streambank planted (C.5.c.4)
 Riparian Plant removal / control (C.5.h.1)    
Acres of riparian treated for plant removal/control (C.5.h.3)
21.50acres16.10acres
Miles of streambank treated for plant removal/control (C.5.h.4)