Chumstick
#Level 2 #Level 2
 Wenatchee Sub-basin Chumstick
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor
Status Active
Schedule Start Date: 1/1/1999 End Date: 1/2/2022
Priority 1
Category Category: 
DESCRIPTION
Show more  ↓
FUNDING
Proposed Cost $6,882,608.59
Requested Funds $0
Allocated Funds $0
Spent Funds $0
Balance $0
FUNDING SOURCES
PROJECT CONTACT
PHOTOS

 
View project on a larger map

Related Projects

ACTIVITY-FISH PASSAGE IMPROVEMENT PCSRF
* Miles of Stream Made Accessible
184%
18.35 Actual
10 Planned
Miles
*Number of Blockages/Impediments/Barriers Impeding Passage
538%
43 Actual
8 Planned
Number
Number of bridges
420%
21 Actual
5 Planned
Number
ACTIVITY-FISH SCREENING PROJECT PCSRF
Number Of Fish Screens Replaced Or Modified 01 Number
ACTIVITY-INSTREAM FLOW PROJECT PCSRF
Acre Feet Of Water Purchased/Leased 18 Acre-Feet
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Miles of Streambank Stabilized
125%
0.1 Actual
0.08 Planned
Miles
Number of structures placed in channel
128%
23 Actual
18 Planned
Number
Total Miles Of Instream Habitat Treated
112%
0.29 Actual
0.26 Planned
Miles
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated
631%
8.84 Actual
1.4 Planned
Acres
* Total Riparian Miles Streambank Treated
1479%
2.07 Actual
0.14 Planned
Miles
Acres Planted in riparian
418%
5.85 Actual
1.4 Planned
Acres
WDFW BARRIER REMOVAL PERMIT ID
WDFW Barrier Removal Permit IDNot entered