Rose Point Embayment Restoration
#20-1525 WSN-2019 #20-1525 WSN-2019
Organization West Sound Partners for Ecosystem Recovery
Sponsor Mid Sound Fisheries Enhancement Group
Status Active
Schedule Start Date: 7/1/2021 End Date: 5/31/2026
Category Category: Restoration
DESCRIPTION
The Mid Sound Fisheries Enhancement Group in partnership with theKitsap Conservation District and two private landowners will restore 470feet of the lower reach and 1 acre of estuary of a small perennial streamand remove 770 feet of creosote piling bulkhead from the nearshore atRose Point near Eglon. This project was originally identified in KitsapCounty's 2016 assessment of priority nearshore projects as a top tierrestoration project. The Kitsap Shore Friendly program has already givena small grant to the northern property owner to do some preliminaryanalysis and design work which is completed. The southern propertyowner is in the process of applying for a Kitsap Conservation DistrictBackyard Habitat grant to restore the lower reach of the freshwater streamon her property including removing reed canary grass, replanting withnative riparian plants, and replacing a bridge that is impacting naturalstream processes. This grant will bring these two efforts together tocomplete final design work, secure necessary permits and construct theproject.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested06/29/2020Mid Sound Fisheries Enhancement GroupMatch$65,795.00
Requested06/29/2020Recreation and Conservation Office (RCO)ESRP Small Projects$150,000.00
Allocated08/30/2024Recreation and Conservation Office (RCO)ESRP Small Projects$92,613.00
Allocated08/30/2024Recreation and Conservation Office (RCO)Salmon State Projects$107,932.00
Allocated08/30/2024Mid Sound Fisheries Enhancement GroupMatch$166,001.00
Allocated08/30/2024Recreation and Conservation Office (RCO)FFFPP Grants$250,627.00
Allocated08/30/2024Recreation and Conservation Office (RCO)Salmon State Supplemental Sm$347,936.00
Allocated08/30/2024Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$808,530.00
Spent03/25/2024Recreation and Conservation Office (RCO)FFFPP Grants-$250,627.00
Spent09/20/2024Recreation and Conservation Office (RCO)ESRP Small Projects-$92,613.00
Spent09/20/2024Recreation and Conservation Office (RCO)Salmon State Projects-$107,932.00
Spent12/10/2024Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$808,530.00
Spent05/13/2025Mid Sound Fisheries Enhancement GroupMatch-$146,207.01
Spent05/13/2025Recreation and Conservation Office (RCO)Salmon State Supplemental Sm-$156,240.90
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$216,000.00 $215,795.00 $1,773,639.00 $1,562,149.91 $211,489.09
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Kitsap
HUC12:Big Valley-Frontal Puget Sound (171100190707)
HUC8:Puget Sound (17110019)
Lead Entity Area:West Sound
Legislative District:23
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:North Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:02
Sections:11
Steelhead-Pop (ESU):Steelhead-Puget Sound, East Kitsap Peninsula Tributaries, Threatened
Township:T27NR02E
Watershed Administrative Unit:Liberty-Miller-Appletree
WRIA:Kitsap
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.10mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
3.00acres
 Beach nourishment (C.9.l.1)    
Acres Treated for beach nourishment (C.9.l.4)
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
 Channel modification (C.9.c.1)    
Acres of Estuary Treated (C.9.c.3)
0.10acres
 Dike Or berm modification / removal (C.9.d.1)    
Acres of Habitat Made Available To Salmonids through dike or berm modification/removal (C.9.d.3)
2.00acres
Miles Of Dikes Modified/Removed (C.9.d.2)
0.15mi
 Estuarine plant removal / control (C.9.j.1)    
Acres of Estuary Treated for plant removal/control (C.9.j.3)
 Estuarine planting or native plant establishment (C.9.r.1)    
Acres of Estuarine planting or native plant establishment (C.9.r.3)
0.50acres
 Removal of existing fill material (C.9.g.1)    
Acres of Estuary Treated through fill material removal (C.9.g.2)
0.50acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.10acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.15mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
Number of bridges (C.2.g.2)
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
Instream Pools Created/Added (C.4.c.6)
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
 Channel structure placement (C.4.d.1)    
Miles of Stream Treated for channel structure placement (C.4.d.3)
Number of structures placed in channel (C.4.d.7)
Pools Created through channel structure placement (C.4.d.5)