DESCRIPTION
The Whidbey Camano Land Trust (Land Trust) and project partners will develop a preliminary design for restoration of critical salmon and wildlife habitat on priority lands in Livingston Bay on Camano Island, and seize upon current acquisition opportunities if restoration is deemed feasible. The Livingston Bay Protection and Restoration Planning project will investigate restoration feasibility of former tidal estuary and wetland habitat that is currently managed as diked farmland, and protect those lands and adjacent nearshore habitat to benefit multiple species of salmonids, including Endangered Species Act listed Puget Sound Chinook salmon and Puget Sound steelhead. The 317 acres targeted for restoration planning includes over three quarters of a mile of Livingston Bay shoreline and 25 acres of tidelands directly adjacent to over 7,500 acres of protected habitat within Port Susan Bay and the Stillaguamish River Delta. At present, up to 200 acres are available for acquisition. The Livingston Bay Protection and Restoration Planning project will advance process-based restoration efforts prioritized by the Puget Sound Nearshore Ecosystem Restoration Project (PSNERP) by building off of the conceptual design work already completed and securing a portion of that project footprint.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested07/24/2020Whidbey Camano Land Trust (WCLT)Match$1,175,000.00
Requested07/24/2020Recreation and Conservation Office (RCO)Estuary & Salmon Restoration$1,500,000.00
Allocated02/12/2025Recreation and Conservation Office (RCO)Salmon State Projects$20,246.00
Allocated02/12/2025Recreation and Conservation Office (RCO)Salmon Federal Projects$304,567.00
Allocated02/12/2025Recreation and Conservation Office (RCO)Salmon State Riparian$445,433.00
Allocated02/12/2025Whidbey Camano Land Trust (WCLT)Match$529,883.00
Allocated02/12/2025Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$624,871.00
Allocated02/12/2025Recreation and Conservation Office (RCO)Estuary & Salmon Restoration$1,500,000.00
Spent12/13/2023Recreation and Conservation Office (RCO)Salmon State Projects-$20,246.00
Spent12/13/2023Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$624,871.00
Spent02/11/2025Recreation and Conservation Office (RCO)Salmon Federal Projects-$304,567.00
Spent02/11/2025Recreation and Conservation Office (RCO)Salmon State Riparian-$402,652.09
Spent02/11/2025Whidbey Camano Land Trust (WCLT)Match-$522,052.96
Spent02/11/2025Recreation and Conservation Office (RCO)Estuary & Salmon Restoration-$1,500,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,450,000.00 $2,675,000.00 $3,425,000.00 $3,374,389.05 $50,610.95
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
SECONDARY SPONSOR CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Island
HUC12:Camano Island (171100190107)
HUC12:Skagit Bay (171100191100)
HUC8:Puget Sound (17110019)
Lead Entity Area:Island County
Legislative District:10
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:20
Sections:21
Sections:28
Sections:29
Skagit Tiers:Tier 2 Pocket Estuaries
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Township:T32NR03E
Watershed Administrative Unit:Camano Island
WRIA:Island
View project on a larger map

Related Projects

  APPLICATION FINAL 
ACQUISTION METRICS
Incidentals    
 Noxious weed control    
Acres treated for noxious weeds by method
Chemical
22.50
Mechanical
22.50
Total
45.00
acres
Biological
0.00
Chemical
20.00
Mechanical
20.00
Total
40.00
acres
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
0.82mi0.32mi
 Easement    
Acres by Acreage Type (easement)
Total
acres
 Land    
Acres by Acreage Type (fee simple)
Uplands
124.87
Wetlands
26.50
Total
151.37
acres
Lake
0.00
Riparian
0.00
Tidelands
0.00
Uplands
111.49
Wetlands
40.65
Total
152.14
acres
 
PLANNING METRICS
Area Encompassed (acres) (B.0.b.1)
317.00acres
Miles of Stream and/or Shoreline Affected (B.0.b.2)
0.94mi
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.82mi