Black River
#Sub Basin #Sub Basin
Organization Chehalis Basin Lead Entity
Sponsor
Status Active
Schedule Start Date: 1/26/2001 End Date: 12/31/2021
Priority 1
Category Category: 
DESCRIPTION
Show more  ↓
FUNDING
Proposed Cost $3,036,347.01
Requested Funds $0
Allocated Funds $0
Spent Funds $0
Balance $0
FUNDING SOURCES
PROJECT CONTACT
GRANT MANAGER
LEAD ENTITY COORDINATOR
PHOTOS

 
View project on a larger map

Related Projects

ACTIVITY-FISH PASSAGE IMPROVEMENT PCSRF
* Miles of Stream Made Accessible
114%
1.97 Actual
1.73 Planned
Miles
*Number of Blockages/Impediments/Barriers Impeding Passage
300%
3 Actual
1 Planned
Number
Number of bridges
150%
3 Actual
2 Planned
Number
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Number of structures placed in channelNot entered
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated
120%
17.4 Actual
14.5 Planned
Acres
* Total Riparian Miles Streambank Treated
100%
2.78 Actual
2.78 Planned
Miles
Acres of riparian treated for plant removal/control
100%
28.3 Actual
28.3 Planned
Acres
Acres Planted in riparian
108%
40.5 Actual
37.5 Planned
Acres
Miles of streambank treated for plant removal/controlNot entered
ACTIVITY-WETLAND PROJECT PCSRF
Total Acres Of Wetland Area Treated
433%
1.3 Actual
0.3 Planned
Acres