Organization | North Pacific Coast Lead Entity |
Sponsor | 10,000 Years Institute |
Status | Active |
Schedule | Start Date: 7/1/2023 End Date: 11/30/2025 |
Category | Category: Planning & Restoration |
The
Pulling Together in Restoration Project (PTIR) is a landscape-scale Jobs-in-Restoration
program working across multiple jurisdictions in three counties to prevent the
spread of invasive species in coastal watersheds. Integrating decades of adaptation, PTIR
develops cutting-edge methods for effective and safe containment, responds
quickly to emerging or untreated needs, and engages in job creation and community-based
education and collaboration to address the challenges of invasive species and
their impacts to climate, habitats, natural resource -based industries, salmon
recovery, and community resiliency.
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 06/09/2022 | 10,000 Years Institute | Match | $129,198.00 | |
Requested | 06/09/2022 | Recreation and Conservation Office (RCO) | WA Coast Rst Resiliency Proj | $1,400,000.00 | |
Allocated | 01/12/2024 | 10,000 Years Institute | Match | $129,198.00 | |
Allocated | 01/12/2024 | Recreation and Conservation Office (RCO) | WA Coast Rst Resiliency Proj | $1,400,000.00 | |
Spent | 10/24/2024 | 10,000 Years Institute | Match | -$118,862.16 | |
Spent | 10/24/2024 | Recreation and Conservation Office (RCO) | WA Coast Rst Resiliency Proj | -$1,288,000.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$0.00 | $1,529,198.00 | $1,529,198.00 | $1,406,862.16 | $122,335.84 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Washington Coast, Not Warranted |
Chum-Pop (ESU): | Chum-Pacific Coast, Not Warranted |
City Areas: | Forks |
Coho-Pop (ESU): | Coho-Olympic Peninsula, Not Warranted |
Coho-Pop (ESU): | Coho-Southwest Washington, Not Determined |
County: | Clallam |
County: | Grays Harbor |
HUC12: | Finley Creek-Quinault River (171001020407) |
HUC12: | Middle Bogachiel River (171001010503) |
HUC12: | Upper Hoko River (171100210703) |
HUC12: | Upper Humptulips River (171001050104) |
HUC8: | Crescent-Hoko (17110021) |
HUC8: | Grays Harbor (17100105) |
HUC8: | Hoh-Quillayute (17100101) |
HUC8: | Queets-Quinault (17100102) |
Lead Entity Area: | Chehalis Basin |
Lead Entity Area: | North Olympic Peninsula |
Lead Entity Area: | North Pacific Coast |
Lead Entity Area: | Quinault Indian Nation |
Legislative District: | 24 |
Puget Sound Action Areas: | Strait of Juan de Fuca |
Salmon Recovery Regions: | Puget Sound |
Salmon Recovery Regions: | Washington Coast |
Sections: | 06 |
Sections: | 09 |
Sections: | 35 |
Sockeye-Pop (ESU): | Sockeye-Quinault Lake, Not Warranted |
Steelhead-Pop (ESU): | Steelhead-Olympic Peninsula, Not Warranted |
Steelhead-Pop (ESU): | Steelhead-Washington Coast, Not Warranted |
Township: | T21NR10W |
Township: | T23NR08W |
Township: | T28NR13W |
Township: | T30NR13W |
Watershed Administrative Unit: | Hoko |
Watershed Administrative Unit: | Lower Calawah |
Watershed Administrative Unit: | Quinault Lake |
Watershed Administrative Unit: | Stevens Creek |
WRIA: | Lower Chehalis |
WRIA: | Lyre - Hoko |
WRIA: | Queets - Quinault |
WRIA: | Soleduc |
APPLICATION | FINAL | ||||
PLANNING/RESTORATION METRICS | |||||
Area Encompassed (acres) (B.0.b.1) | 1,460.00 | acres | 5,895.90 | acres | |
Miles of Stream and/or Shoreline Affected (B.0.b.2) | 120.00 | mi | 96.08 | mi | |
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 163.00 | mi | 96.08 | mi | |
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 57.00 | mi | 63.76 | mi | |
Plant removal/control (C.4.g.1) | |||||
Acres of Streambed Treated for plant removal/control (C.4.g.4) | 42.00 | acres | 227.30 | acres | |
Miles of Stream Treated for plant removal/control (C.4.g.3) | 57.00 | mi | 76.09 | mi | |
Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 950.00 | acres | 863.00 | acres | |
*Total Riparian Miles Streambank Treated (C.5.b.1) | 87.00 | mi | 69.48 | mi | |
Riparian Plant removal / control (C.5.h.1) | |||||
Acres of riparian treated for plant removal/control (C.5.h.3) | 944.00 | acres | 863.00 | acres | |
Miles of streambank treated for plant removal/control (C.5.h.4) | 87.00 | mi | 69.48 | mi | |
Upland Habitat And Sediment Project | |||||
Acres of Upland Habitat Area Treated (C.6.b.1) | 177.00 | acres | 458.30 | acres | |
Miles of Road Treated (C.6.b.2) | 225.00 | mi | 160.76 | mi | |
Upland vegetation management (C.6.h.1) | |||||
Acres Treated for upland vegetation management (C.6.h.3) | 165.00 | acres | 458.30 | acres | |
Wetland Project | |||||
Total Acres Of Wetland Area Treated (C.8.b) | 15.00 | acres | 71.70 | acres | |
Wetland plant removal / control (C.8.d.1) | |||||
Acres of wetland treated for plant removal/control (C.8.d.3) | 15.00 | acres | 71.70 | acres | |
Wetland planting (C.8.c.1) | |||||
Acres of wetland planted (C.8.c.3) | 3.00 | acres | 0.00 | acres |
WCRRI-Conceptual-Project-Form_10KYI_PTIR-5.docx |