This project completed the following actions: 1. Bridge Abutment Fill Removal (Nason Creek RM 4.7): This action removed 1,325 cubic yards (0.14 acre) of fill associated with a relic abutment of a historical bridge. This action restores channel migration potential on river left. 2. Road Approach Floodplain Fill Removal (Nason Creek RM 4.6): This action removed 0.61 acre (1,825 cy) of fill from the Nason Creek floodplain and restores floodplain wetland conditions. 3. Oxbow Enhancement (Nason Creek RM 3.9): This action added 28 pieces of large wood to enhance existing side channel habitat. This project also included 2 years of implementation monitoring and adaptive management actions such as additional survey, hand excavation of material, and supplemental planting. Monitoring efforts included 2 seasons of data collection summarized in a text report and a video to document sediment deposition and subsequent revegetation in the oxbow.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/23/2012Chelan County Natural Resources DepartmentMatch$60,000.00
Requested08/23/2012Recreation and Conservation Office (RCO)Salmon State Projects$338,233.00
Allocated02/17/2017Chelan County Natural Resources DepartmentMatch$59,059.98
Allocated02/17/2017Recreation and Conservation Office (RCO)Salmon State Projects$60,000.00
Allocated02/17/2017Recreation and Conservation Office (RCO)Salmon Federal Projects$272,933.88
Spent08/12/2015Recreation and Conservation Office (RCO)Salmon State Projects-$60,000.00
Spent02/16/2017Chelan County Natural Resources DepartmentMatch-$59,059.98
Spent02/16/2017Recreation and Conservation Office (RCO)Salmon Federal Projects-$272,933.88
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1.00 $398,233.00 $391,993.86 $391,993.86 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Wenatchee River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
County:Chelan
HUC12:Lower Nason Creek (170200110203)
HUC8:Wenatchee (17020011)
Lead Entity Area:Upper Columbia
Legislative District:12
Salmon Recovery Regions:Upper Columbia River
Sections:09
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Wenatchee River, Threatened
Township:T26NR17E
Upper Columbia Assesment Unit:Lower Nason Creek
Watershed Administrative Unit:Lower Nason
WRIA:Wenatchee
View project on a larger map

Related Projects

  APPLICATION FINAL 
PLANNING/RESTORATION METRICS
Area Encompassed (acres) (B.0.b.1)
3.50acres
Miles of Stream and/or Shoreline Affected (B.0.b.2)
0.50mi
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.00mi0.50mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
1.00mi1.00mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
0.60acres0.60acres
Instream Pools Created/Added (C.4.c.6)
0.000.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.04mi0.04mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.00mi0.01mi
 Channel structure placement (C.4.d.1)    
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.01mi0.50mi
Number of structures placed in channel (C.4.d.7)
1.004.00
Pools Created through channel structure placement (C.4.d.5)
1.004.00