Gagnon CMZ Off-Channel Habitat Project
#05-1546 #05-1546
 Wenatchee Sub-basin Lower Wenatchee Gagnon CMZ Off-Channel Habitat Project
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Chelan County Natural Resources Department
Status Completed
Schedule Start Date: 3/1/2006 End Date: 3/26/2009
Priority 1
Category Category: Restoration
Project Photo
DESCRIPTION
The CCNRD has completed the construction of the Gagnon Off-Channel Habitat Project. The Gagnon Project has created approximately .56 acres of off-channel high-flow (>3,000 cfs) refuge and rearing habitat while connecting 0.5 acres of currently isolated high-flow habitat; directly benefiting juvenile Chinook, steelhead, and coho. The project also included 1.39 acres of riparian restoration.
Show more  ↓
FUNDING
Proposed Cost $513,775
Requested Funds $431,325
Allocated Funds $417,936.83
Spent Funds $417,936.83
Balance $0
FUNDING SOURCE
Salmon Recovery Funding Board$417,936.83
FUNDING SOURCES
PROJECT CONTACT
COORDINATOR
GRANT MANAGER
PARTNER
SPONSOR
PHOTOS

 
LOCATION
Legislative District:12
Sections:36
County:Chelan
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Wenatchee River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
HUC12:Ollala Canyon-Wenatchee River (170200110707)
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Wenatchee River, Threatened
Township:T24NR18E
Lead Entity Area:Upper Columbia
Salmon Recovery Regions:Upper Columbia River
WRIA:Wenatchee
HUC8:Wenatchee (17020011)
View project on a larger map
ACTIVITY-FISH PASSAGE IMPROVEMENT PCSRF
* Miles of Stream Made AccessibleNot entered
*Number of Blockages/Impediments/Barriers Impeding Passage 01 Number
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Total Miles Of Instream Habitat Treated
162%
0.13 Actual
0.08 Planned
Miles
Acres Of Off-Channel/Floodplain Connected Or Added 01.1 Acres
Miles of Off-Channel Stream Created 00.13 Miles
Miles of Streambank Stabilized 00.03 Miles
Number of structures placed in channel 22 Number
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated 01.4 Acres
* Total Riparian Miles Streambank Treated 00.13 Miles
Acres of riparian treated for plant removal/controlNot entered
Acres Planted in riparian 01.4 Acres
ACTIVITY-WETLAND PROJECT PCSRF
Total Acres Of Wetland Area TreatedNot entered
FISH
Spring Chinook (Primary)
Summer Steelhead (Secondary)
PROJECT SCHEDULE
2007 Construction
2007 Permitting
SUBBASIN
Wenatchee
ADDITIONAL INFORMATION