| Organization | Upper Columbia Salmon Recovery Board Lead Entity |
| Sponsor | Chelan County Natural Resources Department |
| Status | Dormant |
| Schedule | Start Date: 12/20/2006 End Date: 12/30/2007 |
| Category | Category: Restoration |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|---|---|---|---|---|
| Requested | 09/18/2006 | Chelan County Natural Resources Department | Match | $72,000.00 | |
| Requested | 09/18/2006 | Recreation and Conservation Office (RCO) | Salmon State Projects | $402,642.00 | |
| Allocated | 12/06/2006 | Chelan County Natural Resources Department | Match | $72,000.00 | |
| Allocated | 12/06/2006 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $402,642.00 |
| Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
| $61,919.00 | $474,642.00 | $474,642.00 | $0.00 | $474,642.00 |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|
| Other Funding Totals | Requested | Allocated | Spent | Balance | |
| Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
| Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Wenatchee River, Endangered |
| Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
| County: | Chelan |
| HUC12: | Lower Nason Creek (170200110203) |
| HUC8: | Wenatchee (17020011) |
| Lead Entity Area: | Upper Columbia River |
| Legislative District: | 12 |
| Salmon Recovery Regions: | Upper Columbia River |
| Sections: | 09 |
| Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Wenatchee River, Threatened |
| Township: | T26NR17E |
| Upper Columbia Assesment Unit: | Lower Nason Creek |
| Watershed Administrative Unit: | Lower Nason |
| WRIA: | Wenatchee |
| APPLICATION | FINAL | ||||
| RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.00 | mi | 0.00 | mi | |
| Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | |||||
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | |||||
Square Miles Of streambed made accessible (C.2.b.2) | |||||
| Fish passage blockages removed or altered (C.2.c.1) | |||||
Change in water flow (fish passage project)(cu feet) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | |||||
| Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.80 | mi | 0.00 | mi | |
| Channel reconfiguration and connectivity (C.4.c.1) | |||||
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5) | |||||
Instream Pools Created/Added (C.4.c.6) | |||||
Miles of Off-Channel Stream Created or Connected (C.4.c.4) | |||||
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) | |||||
| Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | |||||
Miles of Stream Treated for channel structure placement (C.4.d.3) | |||||
Number of structures placed in channel (C.4.d.7) | |||||
Pools Created through channel structure placement (C.4.d.5) | |||||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | |||||
| Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.00 | mi | |||
| Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | |||||
*Total Riparian Miles Streambank Treated (C.5.b.1) | |||||
| Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | |||||
Miles of streambank planted (C.5.c.4) | |||||
| Wetland Project | |||||
Total Acres Of Wetland Area Treated (C.8.b) | 34.50 | acres | |||
| Artificial wetland created (C.8.f.1) | |||||
Artificial Wetland Acres Created (C.8.f.2) | 0.00 | acres | |||
| Wetland plant removal / control (C.8.d.1) | |||||
Acres of wetland treated for plant removal/control (C.8.d.3) | 0.00 | acres | |||