Schedule Start Date: 12/13/2007 End Date: 10/28/2011
Category Category: Planning
Project Photo
DESCRIPTION
Snohomish County used this grant to develop a preliminary design and preliminary environmental review for restoration on Smith Island. The restoration work includes breaching up to 5,000 linear feet of dikes, building up to 9,100 linear feet of set back dikes, filling/blocking a drainage ditch network, enhancing tidal channels and their connection to Union Slough, adding logjams, enhancing edge habitat complexity, and planting native vegetation. The project ultimately will restore more than 400 acres of tidal marsh, a significant percentage of the 1,200-acre target in the Snohomish Basin Salmon Conservation Plan. The project will help address the loss of about 85 percent of the basin’s estuarine wetlands, a key factor contributing to the decline of Chinook salmon.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/20/2007Snohomish CountyMatch$55,000.00
Requested09/20/2007Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$300,000.00
Allocated12/13/2007Snohomish CountyMatch$55,000.00
Allocated12/13/2007Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$300,000.00
Spent08/17/2010Snohomish CountyMatch-$55,000.00
Spent08/17/2010Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$300,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$759,800.00 $355,000.00 $355,000.00 $355,000.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Skykomish River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Snohomish
HUC12:Snohomish River-Frontal Possession Sound (171100110203)
HUC8:Snohomish (17110011)
Lead Entity Area:Snohomish Basin
Legislative District:38
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Pink2-Pop (ESU):Pink-Even Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:09
Snohomish Strategy Group:Estuary restoration
Snohomish Subbasins:Snohomish Estuary
Steelhead-Pop (ESU):Steelhead-Puget Sound, Snohomish/Skykomish Rivers, Threatened
Township:T29NR05E
Watershed Administrative Unit:Everett
WRIA:Snohomish
View project on a larger map

Related Projects

  APPLICATION FINAL 
PLANNING METRICS
Area Encompassed (acres) (B.0.b.1)
400.00acres
Miles of Stream and/or Shoreline Affected (B.0.b.2)