Greenwater LWD Phase II
#07-1867 #07-1867
 WRIA 10 Greenwater River Greenwater LWD Phase II
Organization Puyallup and Chambers Watershed Salmon Recovery Lead Entity
Sponsor South Puget Sound Salmon Enhancement Group (SPSSEG)
Status Completed
Schedule Start Date: 4/1/2008 End Date: 11/28/2011
Category Category: Restoration
Project Photo
DESCRIPTION
This project built upon Engineered Log Jam (ELJ) and road removal work already funded through the SRFB in 2006 and completed in 2010. In 2010 five engineered log jams were placed and 3/4 of a mile section of road was removed from the floodplain. This project contiued work downstream through the installation of 8 more mid-channel engineered log jams and removal of the remaining 1/4 section of road. In total, this phase II project placed 336 key pieces logs, 1200 racking logs, 1600 cubic yards of slash, and removed 27,000 cubic yards of road fill and armor rock from the floodplain. These structures are placed with the intent to successfully restore the channel vertical elevation, promote lateral movement and floodplain connectivity, increase gravel sorting and retention, and provide pool habitat for adult and juvenile fish. This project will jump-start recovery of critical salmon habitat lost in the 1970s when much of the watershed was altered by removing virtually all standing and instream trees from the Greenwater Valley, for the purpose of recovering Puyallup River salmon stocks as identified in the WRIA 10 Salmon Recovery Strategy.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested10/19/2007South Puget Sound Salmon Enhancement Group (SPSSEG)Match$60,000.00
Requested10/19/2007Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$340,000.00
Allocated11/26/2010South Puget Sound Salmon Enhancement Group (SPSSEG)Match$104,150.00
Allocated11/26/2010Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$590,000.00
Spent11/28/2011South Puget Sound Salmon Enhancement Group (SPSSEG)Match-$104,150.00
Spent11/28/2011Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$590,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,110,150.00 $400,000.00 $694,150.00 $694,150.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Requested03/20/2018National Oceanic and Atmospheric Administration - Fisheries (NOAA)Natural Resource Damage Assessment and RestorationMatch$313,000.00
Requested03/20/2018Puyallup Tribe of IndiansMatch$103,000.00
Allocated03/20/2018National Oceanic and Atmospheric Administration - Fisheries (NOAA)Natural Resource Damage Assessment and RestorationMatch$313,000.00
Allocated03/20/2018Puyallup Tribe of IndiansMatch$103,000.00
Spent03/20/2018National Oceanic and Atmospheric Administration - Fisheries (NOAA)Natural Resource Damage Assessment and RestorationMatch-$313,000.00
Spent03/20/2018Puyallup Tribe of IndiansMatch-$103,000.00
Other Funding Totals Proposed Requested Allocated Spent Balance
$0.00 $416,000.00 $416,000.00 $416,000.00 $0.00
Grand Totals Proposed Requested Allocated Spent Balance
$1,110,150.00 $816,000.00 $1,110,150.00 $1,110,150.00 $0.00
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, White River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:King
County:Pierce
HUC12:Lower Greenwater River (171100140306)
HUC8:Puyallup (17110014)
Lead Entity Area:Pierce County
Legislative District:05
Legislative District:31
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:21
Sections:22
Steelhead-Pop (ESU):Steelhead-Puget Sound, White River, Threatened
Township:T19NR10E
Watershed Administrative Unit:Greenwater
WRIA:Puyallup - White
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
3.00mi0.50mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
3.00mi0.50mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
5.00acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.50mi
Number of structures placed in channel (C.4.d.7)
8.00
Pools Created through channel structure placement (C.4.d.5)
8.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
9.00yd
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
0.00mi0.50mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
1.20acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.50mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
1.20acres
ADDITIONAL INFORMATION