Organization | West Sound Partners for Ecosystem Recovery |
Sponsor | Kitsap Conservation District |
Status | Completed |
Schedule | Start Date: 11/14/2012 End Date: 11/30/2013 |
Category | Category: Restoration |
Illahee Creek has experienced problems associated with excessive sediment bedload transport due to urbanization. Though the project site has been planted with 1500 cedar trees, the stream still lacks channel complexity and suitable salmon habitat. Installation of LWD will remedy instream habitat issues and help control sediment transport.
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 03/26/2013 | Kitsap County Public Works | $10,000.00 | ||
Allocated | 03/26/2013 | Kitsap County Public Works | $10,000.00 | ||
Spent | 04/08/2015 | Kitsap County Public Works | -$10,000.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$10,000.00 | $10,000.00 | $10,000.00 | $10,000.00 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Requested | Allocated | Spent | Balance | |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Kitsap |
HUC12: | Barker Creek-Frontal Dyes Inlet (171100190706) |
HUC8: | Puget Sound (17110019) |
Lead Entity Area: | West Sound Watersheds |
Legislative District: | 23 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | North Central Puget Sound |
Salmon Recovery Regions: | Puget Sound |
Sections: | 31 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, East Kitsap Peninsula Tributaries, Threatened |
Township: | T25NR02E |
Watershed Administrative Unit: | Dyes Inlet |
WRIA: | Kitsap |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | |||||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.01 | mi | 0.01 | mi | |
Channel reconfiguration and connectivity (C.4.c.1) | |||||
Instream Pools Created/Added (C.4.c.6) | 8.00 | 8.00 | |||
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) | 0.01 | mi | 0.01 | mi | |
Channel structure placement (C.4.d.1) | |||||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.01 | mi | 0.01 | mi | |
Number of structures placed in channel (C.4.d.7) | 8.00 | 8.00 | |||
Pools Created through channel structure placement (C.4.d.5) | 8.00 | 8.00 | |||
Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 0.80 | acres | 0.80 | acres | |
*Total Riparian Miles Streambank Treated (C.5.b.1) | 0.01 | mi | 0.01 | mi | |
Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | 0.80 | acres | 0.80 | acres |
![]() | Krigsman_Backyard_Habitat_Maps |