Organization | West Sound Partners for Ecosystem Recovery |
Sponsor | Kitsap Conservation District |
Status | Completed |
Schedule | Start Date: 12/12/2008 End Date: 3/21/2011 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 03/16/2009 | Recreation and Conservation Office (RCO) | FFFPP Grants | $111,224.00 | |
Allocated | 03/21/2011 | Recreation and Conservation Office (RCO) | FFFPP Grants | $104,210.87 | |
Spent | 03/11/2011 | Kitsap Conservation District | Match | -$0.00 | |
Spent | 03/11/2011 | Recreation and Conservation Office (RCO) | FFFPP Grants | -$104,210.87 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$111,224.00 | $111,224.00 | $104,210.87 | $104,210.87 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
City Areas: | Silverdale |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Kitsap |
HUC12: | Barker Creek-Frontal Dyes Inlet (171100190706) |
HUC8: | Puget Sound (17110019) |
Lead Entity Area: | West Sound |
Legislative District: | 23 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | North Central Puget Sound |
Salmon Recovery Regions: | Puget Sound |
Sections: | 15 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, East Kitsap Peninsula Tributaries, Threatened |
Township: | T25NR01E |
Watershed Administrative Unit: | Dyes Inlet |
WRIA: | Kitsap |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.00 | mi | 0.01 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 0.54 | mi | 0.54 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | ||||
Miles Of Stream Made Accessible (FFFPP) | |||||
Square Miles Of streambed made accessible (C.2.b.2) | 1.00 | sq mi | |||
Bridge installed or improved (C.2.g.1) | |||||
Miles of stream made accessible by bridge installation/repair (C.2.g.3) | 0.54 | mi | |||
Number of bridges (C.2.g.2) | 1.00 | ||||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.01 | mi | |||
Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | 0.10 | acres | |||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.01 | mi | |||
Number of structures placed in channel (C.4.d.7) | 10.00 | ||||
Pools Created through channel structure placement (C.4.d.5) | 10.00 | ||||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | 2.00 | yd |
![]() | Final design |
![]() | Project site |
![]() | WRIA 15 habitat map |
![]() | FFFPP agreement |