Organization | Island County Lead Entity |
Sponsor | Island County |
Status | Dormant |
Schedule | Start Date: 2/15/2001 End Date: 5/30/2005 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 11/15/2000 | Island County | Match | $102,200.00 | |
Requested | 11/15/2000 | Recreation and Conservation Office (RCO) | Salmon State Projects | $443,849.00 | |
Allocated | 05/17/2005 | Island County | Match | $102,570.25 | |
Allocated | 05/17/2005 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $264,673.61 | |
Spent | 05/17/2005 | Island County | Match | -$102,570.25 | |
Spent | 05/17/2005 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | -$264,673.61 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$367,243.86 | $546,049.00 | $367,243.86 | $367,243.86 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
City Areas: | Oak Harbor |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Island |
HUC12: | Skagit Bay (171100191100) |
HUC12: | Whidbey Island-Frontal Saratoga Passage (171100190103) |
HUC8: | Puget Sound (17110019) |
Lead Entity Area: | Island County |
Legislative District: | 10 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | Whidbey Island |
Salmon Recovery Regions: | Puget Sound |
Sections: | 31 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Threatened |
Township: | T33NR02E |
Watershed Administrative Unit: | Whidbey Island |
WRIA: | Island |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.15 | mi | 0.00 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | |||||
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | |||||
Square Miles Of streambed made accessible (C.2.b.2) | |||||
Fish passage blockages removed or altered (C.2.c.1) | |||||
Change in water flow (fish passage project)(cu feet) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | |||||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.00 | mi | 0.00 | mi | |
Channel reconfiguration and connectivity (C.4.c.1) | |||||
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5) | |||||
Instream Pools Created/Added (C.4.c.6) | |||||
Miles of Off-Channel Stream Created or Connected (C.4.c.4) | |||||
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) | |||||
Plant removal/control (C.4.g.1) | |||||
Acres of Streambed Treated for plant removal/control (C.4.g.4) | |||||
Miles of Stream Treated for plant removal/control (C.4.g.3) | |||||
Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.00 | mi | 0.00 | mi | |
Wetland Project | |||||
Total Acres Of Wetland Area Treated (C.8.b) | 150.00 | acres | 0.00 | acres | |
Artificial wetland created (C.8.f.1) | |||||
Artificial Wetland Acres Created (C.8.f.2) | 0.00 | acres | 0.00 | acres | |
Wetland plant removal / control (C.8.d.1) | |||||
Acres of wetland treated for plant removal/control (C.8.d.3) | 0.00 | acres | 0.00 | acres |