Ala Spit Restoration, Phase 4
#06-NP-14-004 #06-NP-14-004
Organization Island County Lead Entity
Sponsor Island County Public Works
Status Completed
Schedule Start Date: 9/18/2014 End Date: 2/23/2016
Category Category: Restoration
Project Photo
DESCRIPTION
Phase 4 of the Ala Spit restoration will consist of rebuilding the neck of the spit, removal of the bulkhead and modification of the rock groin. Construction is Aug 24-Sept 24. This project will construct the preferred alternative identified in the feasibility study (12-1260), which evaluated options for the rock groin and final bulkhead section (435') removal to complete the restoration efforts at Ala Spit County Park. The bulkhead in front of the parking lot will remain in response to stakeholders concerns.Rock groin modification will restore the littoral transport to the Ala Spit drift cell, as well as add to the aesthetic value of the part as a natural place, while protecting nearby private property. A portion of the rock groin will be relocated landward and to the south to provide protection of the bluff toe in the area water-ward of the adjacent house. Beach nourishment will be added to the site to benefit the spit neck stability and improve habitat. Restoration activities will result in nearly full sediment transport processes restoration, immediate gain of upper beach habitat through direct removal of the entire rock groin, and re-connection of the upland with the beach due to the removal of the bulkhead. Restoration will also result in enhanced recreation and improved conditions in terms of risk management, as park users will no longer be required to traverse the large rock groin and vertical bulkhead south of the parking area, and will also not be require to wade th
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested03/18/2014Island County Public WorksMatch$53,600.00
Requested03/18/2014Recreation and Conservation Office (RCO)Salmon State Projects$262,800.00
Allocated07/07/2015Island County Public WorksMatch$72,850.00
Allocated07/07/2015Recreation and Conservation Office (RCO)Salmon Federal Projects$75,809.00
Allocated07/07/2015Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$336,991.00
Spent02/23/2016Island County Public WorksMatch-$72,850.00
Spent02/23/2016Recreation and Conservation Office (RCO)Salmon Federal Projects-$75,809.00
Spent02/23/2016Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$336,991.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$485,650.00 $316,400.00 $485,650.00 $485,650.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Island
HUC12:Skagit Bay (171100191100)
HUC12:Whidbey Island-Frontal Skagit Bay (171100190102)
HUC8:Puget Sound (17110019)
Lead Entity Area:Island County
Legislative District:10
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:32
Skagit Tiers:Tier 2 Pocket Estuaries
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Township:T34NR02E
Watershed Administrative Unit:Whidbey Island
WRIA:Island
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.01mi0.01mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
0.40acres1.90acres
 Beach nourishment (C.9.l.1)    
Acres Treated for beach nourishment (C.9.l.4)
0.40acres0.40acres
Cubic Yards Of Beach Substrate Placed (C.9.l.2)
2,300.00cubic yds2,300.00cubic yds
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
0.08mi0.08mi
 Regrading of slope (C.9.i.1)    
Acres of Estuary Treated through slope regrading (C.9.i.2)
1.90acres1.90acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
1.90acres1.90acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.05mi0.05mi
ADDITIONAL INFORMATION