Jimmycomelately Nearshore Restoration
#Rest(JCL)-89714 #Rest(JCL)-89714
 WRIA17: Sequim Bay & Drainages Jimmycomelately Creek Jimmycomelately Nearshore Restoration
Organization North Olympic Peninsula Lead Entity for Salmon
Sponsor Jamestown S'Klallam Tribe
Status Completed
Schedule Start Date: 7/1/2003 End Date: 11/10/2005
Category Category: Restoration
Project Photo
DESCRIPTION
The Jimmycomelately Project was an attempt to remove, to the extent possible, human infrastructure and stressors on the Jimmycomelately-Sequim Bay ecosystem and thereby restore more natural ecosystem processes and functions. Stated simply, the partners dubbed the project: -A vision of undevelopment. The sense of a unified vision among the 27 project partners not only gave the project needed momentum, but also led to the cooperative spirit that was a hallmark of this landscape-scale restoration project.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested07/01/2002US Fish & Wildlife Service (USFWS)$327,914.08
Requested07/01/2002US Environmental Protection Agency (EPA)$327,914.08
Allocated10/04/2005US Fish & Wildlife Service (USFWS)$327,914.08
Allocated10/04/2005US Environmental Protection Agency (EPA)$327,914.08
Spent10/04/2005US Environmental Protection Agency (EPA)-$327,914.08
Spent10/04/2005US Fish & Wildlife Service (USFWS)-$327,914.08
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$6,957,500.00 $655,828.16 $655,828.16 $655,828.16 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
ALT PROJECT CONTACT
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Blyn
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Clallam
HUC12:Discovery Bay-Strait of Juan De Fuca (171100200700)
HUC8:Dungeness-Elwha (17110020)
Lead Entity Area:North Olympic Peninsula
Legislative District:24
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Strait of Juan de Fuca
Salmon Recovery Regions:Hood Canal
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Watershed Administrative Unit:Sequim Bay
WRIA:Quilcene - Snow
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
16.50acres16.50acres
 Dike Or berm modification / removal (C.9.d.1)    
Miles Of Dikes Modified/Removed (C.9.d.2)
0.36mi0.36mi
 Removal of existing fill material (C.9.g.1)    
Acres of Estuary Treated through fill material removal (C.9.g.2)
16.00acres16.00acres
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.90mi0.90mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
50.00acres50.00acres
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.90mi0.90mi
 Channel structure placement (C.4.d.1)    
Number of structures placed in channel (C.4.d.7)
700.00700.00
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
9.00acres9.00acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.75mi0.75mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
9.00acres9.00acres
ADDITIONAL INFORMATION