Deep Cr & SF Pysht Riv LWD Restoration
#02-1583 #02-1583
 WRIA19 Creeks of Central Strait of Juan de Fuca Deep Cr & SF Pysht Riv LWD Restoration
Organization North Olympic Peninsula Lead Entity for Salmon
Sponsor Lower Elwha Klallam Tribe
Status Completed
Schedule Start Date: 1/1/2004 End Date: 9/18/2007
Category Category: Restoration
Project Photo
DESCRIPTION
This proposal involves large woody debris (LWD) projects in WRIA 19 streams that have had previous similar projects. In Deep Creek, we constructed 6 channel spanning logjams using ground-based equipment between river mile 0.2-1.3. The logjams will use multiple sizes of large wood to mimic the natural condition in this floodplain migration channel. Logjams were constructed in plain bed morphology habitats. The logjams will slow water velocities through backwatering, while providing boundary conditions that increase local sheer stress on the channel bed resulting in scour pool development. Habitat diversity is expected to increase at logjam sites as plain bed habitats evolve to those seen in pool-riffle type channels. Habitat quality will also increase as pool area expands and complex cover is provided. This proposal represents the fifth in-channel habitat restoration project conducted on Deep Creek by the Tribe since 1997. Two watershed analysis documents (1995/2002) have been completed and are guiding restoration efforts in Deep Creek. For the SF Pysht, we added LWD using both ground based and helicopter assisted placement techniques. LWD was be placed as free key pieces and as constructed logjams. Plain bed channel reaches were targeted for placement in river mile 0.0-0.5, 0.8-2.0, and 4.0-5.5. These are the remaining untreated reaches following previous cooperative restoration projects between Merrill & Ring and the Tribe.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested12/13/2002Lower Elwha Klallam TribeMatch$109,355.00
Requested12/13/2002Recreation and Conservation Office (RCO)Salmon State Projects$619,675.00
Allocated07/02/2003Lower Elwha Klallam TribeMatch$109,355.00
Allocated07/02/2003Recreation and Conservation Office (RCO)Salmon Federal Projects$619,675.00
Spent09/18/2007Lower Elwha Klallam TribeMatch-$109,355.00
Spent09/18/2007Recreation and Conservation Office (RCO)Salmon Federal Projects-$619,675.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$729,030.00 $729,030.00 $729,030.00 $729,030.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
Coho-Pop (ESU):Coho-Olympic Peninsula, Not Warranted
County:Clallam
HUC12:Deep Creek (171100210304)
HUC12:Pysht River (171100210701)
HUC12:Whiskey Creek-Frontal Strait of Juan De Fuca (171100210305)
HUC8:Crescent-Hoko (17110021)
Lead Entity Area:North Olympic Peninsula
Legislative District:24
Puget Sound Action Areas:Strait of Juan de Fuca
Salmon Recovery Regions:Puget Sound
Sections:19
Sections:20
Sections:28
Sections:29
Sections:30
Steelhead-Pop (ESU):Steelhead-Olympic Peninsula, Not Warranted
Township:T31NR10W
Township:T31NR11W
Watershed Administrative Unit: Pysht River
Watershed Administrative Unit:Twin Rivers-Deep Creek
WRIA:Lyre - Hoko
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
5.80mi4.30mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
5.80mi4.30mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
6.00acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
4.30mi
Number of structures placed in channel (C.4.d.7)
126.00
Pools Created through channel structure placement (C.4.d.5)
31.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
50.00yd
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
0.00mi0.00mi