Organization | North Olympic Peninsula Lead Entity for Salmon |
Sponsor | Merrill & Ring |
Status | Completed |
Schedule | Start Date: 5/31/2002 End Date: 8/17/2005 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | Merrill & Ring | Match | $30,000.00 | ||
Requested | Recreation and Conservation Office (RCO) | Salmon State Projects | $131,900.00 | ||
Allocated | 08/17/2005 | Merrill & Ring | Match | $19,025.00 | |
Allocated | 08/17/2005 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $75,095.37 | |
Spent | 09/30/2003 | Merrill & Ring | Match | -$19,025.00 | |
Spent | 09/30/2003 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | -$75,095.37 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$161,900.00 | $161,900.00 | $94,120.37 | $94,120.37 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Washington Coast, Not Warranted |
Chum-Pop (ESU): | Chum-Pacific Coast, Not Warranted |
Coho-Pop (ESU): | Coho-Olympic Peninsula, Not Warranted |
County: | Clallam |
HUC12: | Pysht River (171100210701) |
HUC8: | Crescent-Hoko (17110021) |
Lead Entity Area: | North Olympic Peninsula |
Legislative District: | 24 |
Puget Sound Action Areas: | Strait of Juan de Fuca |
Salmon Recovery Regions: | Puget Sound |
Sections: | 13 |
Sections: | 34 |
Steelhead-Pop (ESU): | Steelhead-Olympic Peninsula, Not Warranted |
Township: | T31NR11W |
Township: | T31NR12W |
Watershed Administrative Unit: | Pysht River |
WRIA: | Lyre - Hoko |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.60 | mi | 0.60 | mi | |
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.60 | mi | 0.60 | mi | |
Channel reconfiguration and connectivity (C.4.c.1) | |||||
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5) | 0.00 | acres | |||
Instream Pools Created/Added (C.4.c.6) | 10.00 | ||||
Miles of Off-Channel Stream Created or Connected (C.4.c.4) | 0.25 | mi | |||
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) | 0.25 | mi | |||
Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | 0.00 | acres | |||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.60 | mi | |||
Number of structures placed in channel (C.4.d.7) | 20.00 | ||||
Pools Created through channel structure placement (C.4.d.5) | 10.00 | ||||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | 0.00 | yd | |||
Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.00 | mi | 0.60 | mi |
Link to Project Information and Documents (PRISM) | |
Final Report | |
SRFB Agreement |