DESCRIPTION
This project is phase 1 of a 2-phase estuary restoration project. Phase 1 will reconnect 2 slough segments in Quilcene Bay with a 60' Railroad Flat Car Bridge, connect Indian George Creek to the slough, & add scour logs to the lower creek to decrease water velocity. Reconnecting the 2 slough segments, removing accumulated sediments, and adding slough-to-creek access will increase the quality & quantity of estuarine rearing habitat & remove an existing salmonid migration barrier. The southerly slough is cut off from a northerly slough by sediment aggradation caused by a failing culvert, which is also a fish barrier. This affects coho, steelhead, chum, and cutthroat migrating between the creek and the estuary. The culvert will be removed through another funding source, & will be replaced with a 60' RR car bridge reconnecting both slough areas & the creek. This will restore the southern slough habitat functions & increase the quantity of rearing habitat & will increase salmonid access to a 10-acre tidal area, restoring circulation, nutrient distribution, & reduce water temperatures in the slough & nearshore area. Summary: Remove 5' culvert (using another funding source), install 2'x2'x11' abutments, & a 60'x14' RR car bridge, excavate accumulated sediments, add scour logs to lower creek.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested07/16/1999Wild Olympic SalmonMatch$8,000.00
Requested07/16/1999Recreation and Conservation Office (RCO)Salmon State Projects$20,000.00
Allocated12/20/1999Wild Olympic SalmonMatch$8,200.29
Allocated12/20/1999Recreation and Conservation Office (RCO)Salmon State Projects$20,000.00
Spent12/09/1999Wild Olympic SalmonMatch-$8,200.29
Spent12/09/1999Recreation and Conservation Office (RCO)Salmon State Projects-$20,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$28,000.00 $28,000.00 $28,200.29 $28,200.29 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Hood Canal, Hood Canal, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Quilcene
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Jefferson
HUC12:Hood Canal (171100180800)
HUC12:Spencer Creek-Frontal Dabob Bay (171100180701)
HUC8:Hood Canal (17110018)
Lead Entity Area:Hood Canal
Legislative District:24
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Hood Canal
Salmon Recovery Regions:Hood Canal
Sections:25
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Steelhead-Pop (ESU):Steelhead-Puget Sound, West Hood Canal Tributaries, Threatened
Township:T27NR02W
Watershed Administrative Unit:Big Quil
WRIA:Quilcene - Snow
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.10mi0.10mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
1.10acres
 Culvert modification / removal (C.9.f.1)    
Acres Opened To Fish Passage through culvert modification/removal (C.9.f.3)
1.00acres
Number of Culverts Modified/Removed To Allow Fish Passage (C.9.f.2)
1.00
 Removal of existing fill material (C.9.g.1)    
Acres of Estuary Treated through fill material removal (C.9.g.2)
0.10acres
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
13.00mi13.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
Square Miles Of streambed made accessible (C.2.b.2)
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
13.00mi
Number of bridges (C.2.g.2)
1.00
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
1.001.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.00mi0.00mi
Number of road-crossings (C.2.i.2)
ADDITIONAL INFORMATION