Lower Tahuya LWD Placement
#12-01-14735 #12-01-14735
Organization Hood Canal Coordinating Council Lead Entity
Sponsor Hood Canal Salmon Enhancement Group (HCSEG)
Status Completed
Schedule Start Date: 6/1/2011 End Date: 6/29/2012
Category Category: Restoration
Project Photo
DESCRIPTION
The HCSEG completed a watershed assessment and woody debris design project in 2009 for the Lower Tahuya River. Six reaches were identified and analyzed for condition and goals/objectives were developed for each reach. Additionally, multiple sites were selected within each reach for woody debris placement to meet those objectives, while each site was rated as to the level of function that would be restored. Origionally, Reach 6 was selected as the highest priority reach because it has undergone the most extensive widening and gravel aggradation. However, Reach 4, the lower storage reach, has undergone comparably extensive widening and gravel aggradation, and is where the majority of summer chum spawning occurs. Thus, it was selected as the initial starting point for restoration of the Tahuya River because we felt that summer chum salmon would benefit the most from the restoration of this reach. The goal of the project is to improve rearing, spawning, and egg-incubating habitat for all salmonid species in the Tahuya River, while the objective outlined in the assessment is to provide sufficient quantities of long-lasting coniferous wood to improve channel stability and protect/improve habitat quality. LWD will stabilize and trap gravel, improve channel stability and form, and create pools and shade.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/25/2010Hood Canal Salmon Enhancement Group (HCSEG)Match$100,000.00
Requested08/25/2010Recreation and Conservation Office (RCO)Salmon State Projects$103,014.00
Allocated01/09/2014Hood Canal Salmon Enhancement Group (HCSEG)Match$69,090.87
Allocated01/09/2014Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$71,173.96
Spent01/09/2014Hood Canal Salmon Enhancement Group (HCSEG)Match-$69,090.87
Spent01/09/2014Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$71,173.96
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$189,859.00 $203,014.00 $140,264.83 $140,264.83 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Hood Canal, Hood Canal, Threatened
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Mason
HUC12:Tahuya River (171100180104)
HUC8:Hood Canal (17110018)
Lead Entity Area:Hood Canal
Legislative District:35
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Hood Canal
Salmon Recovery Regions:Hood Canal
Sections:07
Sections:13
Sections:14
Sections:23
Steelhead-Pop (ESU):Steelhead-Puget Sound, South Hood Canal Tributaries, Threatened
Township:T22NR02W
Township:T22NR03W
Watershed Administrative Unit:Great Bend
WRIA:Kitsap
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
4.50mi4.50mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.32mi0.37mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
0.50acres0.50acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.32mi0.37mi
Number of structures placed in channel (C.4.d.7)
4.0012.00
Pools Created through channel structure placement (C.4.d.5)
4.004.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
20.00yd20.00yd
 Spawning gravel placement (C.4.f.1)    
Cubic Yards of spawning gravel placed (C.4.f.3)
20.00cubic yds20.00cubic yds
Miles of Stream Treated with spawning gravel placement (C.4.f.2)
0.32mi0.32mi
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
0.32mi0.32mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
0.50acres4.30acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.32mi1.49mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
0.50acres4.30acres
ADDITIONAL INFORMATION