Dosewallips Estuary Restoration Ph 1
#04-03-1073 #04-03-1073
Organization Hood Canal Coordinating Council Lead Entity
Sponsor Wild Fish Conservancy
Status Completed
Schedule Start Date: 6/1/2003 End Date: 12/4/2009
Category Category: Acquisition & Restoration
Project Photo
DESCRIPTION
The historic dike system constructed on the salt marsh face by a previous landowner was meant to increase marginal pasture land for a dairy farm. However, construction of the dike system also decreased tidal inundation which resulted in decreased tidal channel complexity and robustness, in addition to altering the vegetation community on the marsh face and in the upper shrub community. Removal of one half of the dike sytem has been completed with a small excavator and hand crew and results are being monitored. Update: Under phase 1, we removed 1,000 feet of an estuarine dike restoring 40 acres of salt marsh, removed exotic blackberry and replanted native tree and shrub species on 5 acres, designed and installed two interpretive signs, and developed a conceptual reach analysis to guide the phase 2 work.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested12/09/2002Wild Fish ConservancyMatch$31,000.00
Requested12/09/2002Recreation and Conservation Office (RCO)Salmon State Projects$165,017.00
Allocated12/03/2009Wild Fish ConservancyMatch$28,318.28
Allocated12/03/2009Recreation and Conservation Office (RCO)Salmon State Projects$147,702.39
Spent11/29/2005Wild Fish ConservancyMatch-$28,318.28
Spent11/29/2005Recreation and Conservation Office (RCO)Salmon State Projects-$147,702.39
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$176,021.00 $196,017.00 $176,020.67 $176,020.67 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Hood Canal, Hood Canal, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Brinnon
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Jefferson
HUC12:Hood Canal (171100180800)
HUC12:Spencer Creek-Frontal Dabob Bay (171100180701)
HUC8:Hood Canal (17110018)
Lead Entity Area:Hood Canal
Legislative District:24
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Hood Canal
Salmon Recovery Regions:Hood Canal
Sections:02
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Steelhead-Pop (ESU):Steelhead-Puget Sound, West Hood Canal Tributaries, Threatened
Township:T25NR02W
Watershed Administrative Unit:Lower Dosewallips
WRIA:Skokomish - Dosewallips
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.50mi0.50mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
21.00acres21.00acres
 Channel modification (C.9.c.1)    
Acres of Estuary Treated (C.9.c.3)
0.00acres
Yards (linear measure) of Channel Modified/Created (C.9.c.2)
0.00yd
 Creation of new estuarine area (C.9.q.1)    
Acres of Estuary Created (C.9.q.2)
12.00acres0.00acres
 Dike Or berm modification / removal (C.9.d.1)    
Acres of Habitat Made Available To Salmonids through dike or berm modification/removal (C.9.d.3)
5.00acres
Miles Of Dikes Modified/Removed (C.9.d.2)
0.20mi
 Estuarine plant removal / control (C.9.j.1)    
Acres of Estuary Treated for plant removal/control (C.9.j.3)
15.00acres5.00acres
Real Property Acquisition    
 Acquisition or lease of land, wetland or estuarine for conservation (C.10.c.1)    
Acres Of Land, Wetland Or Estuarine Area Conserved By Acquisition Or Lease (C.10.c.6)
Miles Of Streambank Protected By Land or Easement Acquisition (C.10.c.5)