Newskah Trib at Newskah Road 2 Fish Passage Const
#22-1042 #22-1042
Organization Chehalis Basin Lead Entity
Sponsor Chehalis Basin Fisheries Task Force (CBFTF)
Status Active
Schedule Start Date: 9/22/2022 End Date: 5/1/2025
Category Category: Restoration
DESCRIPTION

The problem is a 0% passable fish passage barrier culvert under Newskah Road on an unnamed tributary to Newskah Creek south of Aberdeen in the South Bay Subbasin. The degraded watershed process this project addresses is fish migration access to upstream spawning and rearing habitat. The solution is to remove the barrier culvert and replace it with a structure that is passable to all species and life stages of salmonids and other aquatic species in the tributary. Project designs are complete and permits have been issued under SRFB Grant #19-1185.

Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested03/12/2022Recreation and Conservation Office (RCO)Salmon State Projects$75,053.00
Requested03/12/2022Chehalis Basin Fisheries Task Force (CBFTF)Match$675,482.00
Allocated08/16/2023Recreation and Conservation Office (RCO)Salmon State Supplemental Sm$75,053.00
Allocated08/16/2023Chehalis Basin Fisheries Task Force (CBFTF)Match$112,580.00
Allocated08/16/2023Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board$562,902.00
Spent07/24/2024Recreation and Conservation Office (RCO)Salmon State Supplemental Sm-$75,053.00
Spent10/24/2024Chehalis Basin Fisheries Task Force (CBFTF)Match-$91,679.78
Spent10/24/2024Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board-$444,467.13
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$536,151.00 $750,535.00 $750,535.00 $611,199.91 $139,335.09
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chehalis GSU:Newskah Creek
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
Coho-Pop (ESU):Coho-Southwest Washington, Not Determined
County:Grays Harbor
HUC12:Newskah Creek-Frontal Grays Harbor (171001050301)
HUC8:Grays Harbor (17100105)
Lead Entity Area:Chehalis Basin
Legislative District:19
Salmon Recovery Regions:Washington Coast
Sections:04
Steelhead-Pop (ESU):Steelhead-Washington Coast, Not Warranted
Township:T16NR09W
Watershed Administrative Unit:Johns River
WRIA:Lower Chehalis
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.34mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
1.34mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
1.34mi
Number of culverts (C.2.f.2)
1.00
ADDITIONAL INFORMATION