| Organization | Chehalis Basin Lead Entity |
| Sponsor | Lewis Conservation District |
| Status | Completed |
| Schedule | Start Date: 6/1/2012 End Date: 1/21/2014 |
| Category | Category: Restoration |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|---|---|---|---|---|
| Requested | 12/26/2012 | Recreation and Conservation Office (RCO) | FFFPP Grants | $84,270.00 | |
| Allocated | 01/21/2014 | Recreation and Conservation Office (RCO) | FFFPP Grants | $75,524.11 | |
| Spent | 01/21/2014 | Lewis Conservation District | Match | -$0.00 | |
| Spent | 01/21/2014 | Recreation and Conservation Office (RCO) | FFFPP Grants | -$75,524.11 |
| Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
| $84,270.00 | $84,270.00 | $75,524.11 | $75,524.11 | $0.00 |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|
| Other Funding Totals | Requested | Allocated | Spent | Balance | |
| Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
| Chehalis GSU: | Van Ornum Creek |
| Chinook-Pop (ESU): | Chinook-Washington Coast, Not Warranted |
| Chum-Pop (ESU): | Chum-Pacific Coast, Not Warranted |
| Coho-Pop (ESU): | Coho-Southwest Washington, Not Determined |
| County: | Lewis |
| HUC12: | Mill Creek-Chehalis River (171001030111) |
| HUC8: | Upper Chehalis (17100103) |
| Lead Entity Area: | Chehalis Basin |
| Legislative District: | 19 |
| Salmon Recovery Regions: | Washington Coast |
| Sections: | 32 |
| Steelhead-Pop (ESU): | Steelhead-Washington Coast, Not Warranted |
| Township: | T14NR03W |
| Watershed Administrative Unit: | Bunker Creek |
| WRIA: | Upper Chehalis |
| APPLICATION | FINAL | ||||
| RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.01 | mi | 0.01 | mi | |
| Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 4.68 | mi | 4.68 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | ||||
Miles Of Stream Made Accessible (FFFPP) | |||||
Square Miles Of streambed made accessible (C.2.b.2) | 0.10 | sq mi | 0.10 | sq mi | |
| Bridge installed or improved (C.2.g.1) | |||||
Miles of stream made accessible by bridge installation/repair (C.2.g.3) | 4.68 | mi | 4.68 | mi | |
Number of bridges (C.2.g.2) | 1.00 | 1.00 | |||