| Organization | Chehalis Basin Lead Entity |
| Sponsor | Lewis County Public Works |
| Status | Completed |
| Schedule | Start Date: 1/19/2018 End Date: 12/2/2019 |
| Category | Category: Restoration |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|---|---|---|---|---|
| Requested | 04/09/2018 | Recreation and Conservation Office (RCO) | CBS Habitat Rest. Project | $768,194.00 | |
| Allocated | 04/09/2018 | Recreation and Conservation Office (RCO) | CBS Habitat Rest. Project | $768,194.00 | |
| Spent | 11/26/2019 | Lewis County Public Works | Match | -$0.00 | |
| Spent | 11/26/2019 | Recreation and Conservation Office (RCO) | CBS Habitat Rest. Project | -$768,194.00 |
| Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
| $768,194.00 | $768,194.00 | $768,194.00 | $768,194.00 | $0.00 |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|
| Other Funding Totals | Requested | Allocated | Spent | Balance | |
| Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
| Chehalis GSU: | Bunker Cr |
| Chinook-Pop (ESU): | Chinook-Washington Coast, Not Warranted |
| Chum-Pop (ESU): | Chum-Pacific Coast, Not Warranted |
| Coho-Pop (ESU): | Coho-Southwest Washington, Not Determined |
| County: | Lewis |
| HUC12: | Bunker Creek (171001030109) |
| HUC8: | Upper Chehalis (17100103) |
| Lead Entity Area: | Chehalis Basin |
| Legislative District: | 19 |
| Salmon Recovery Regions: | Washington Coast |
| Sections: | 26 |
| Steelhead-Pop (ESU): | Steelhead-Washington Coast, Not Warranted |
| Township: | T14NR04W |
| Watershed Administrative Unit: | Bunker Creek |
| WRIA: | Upper Chehalis |
| APPLICATION | FINAL | ||||
| RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.03 | mi | 0.04 | mi | |
| Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 4.75 | mi | 4.75 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | 1.00 | |||
| Culvert installed or improved (C.2.f.1) | |||||
Miles of stream made accessible by culvert installation/repair (C.2.f.3) | 4.75 | mi | 4.75 | mi | |
Number of culverts (C.2.f.2) | 1.00 | 1.00 | |||
| Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.00 | mi | 0.00 | mi | |
| Channel structure placement (C.4.d.1) | |||||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.00 | mi | 0.00 | mi | |
Number of structures placed in channel (C.4.d.7) | 7.00 | 7.00 | |||
Pools Created through channel structure placement (C.4.d.5) | 0.00 | 0.00 | |||