Cedar Creek Culvert Replacement
#05-1448 #05-1448
Organization Kalispel Tribe-Pend Oreille Lead Entity
Sponsor Pend Oreille Conservation District
Status Completed
Schedule Start Date: 3/1/2007 End Date: 5/15/2009
Category Category: Restoration
Project Photo
DESCRIPTION
Pend Oreille Conservation District used this funding to remove two side-by-side culverts and a ford that were partial barriers to fish passage on Cedar Creek. The project improved fish passage to approximately 3.75 miles of bull trout and west slope cutthroat trout habitat, including USFWS designated bull trout Critical Habitat located in the immediate vicinity of the project area. Cedar Creek is a tributary to the Pend Oreille River in northeastern Washington State (WRIA 62). Historically, bull trout from the Pend Oreille River and Lake Pend Oreille spawned and reared in WRIA 62 tributaries such as Cedar Creek. Bull trout have been found in Cedar Creek in recent years (1995 and 2003). In 2005, the Cedar Creek Dam, which blocked fish passage to this reach of Cedar Creek, was removed with SRFB funding. With the dam gone, these partial fish passage barriers became priorities for removal to allow unimpeded access to the entire Cedar Creek watershed upstream of the dam. Removal of fish passage barriers (both full and partial) is identified in the Pend Oreille Lead Entity strategy as the #2 priority action for bull trout habitat restoration in the Cedar Creek subbasin, a high priority area in WRIA 62 (ranked #4 of 38).
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/30/2005Pend Oreille Conservation DistrictMatch$13,553.00
Requested09/30/2005Recreation and Conservation Office (RCO)Salmon State Projects$76,797.00
Allocated01/06/2006Pend Oreille Conservation DistrictMatch$13,553.00
Allocated01/06/2006Recreation and Conservation Office (RCO)Salmon State Projects$76,797.00
Spent12/09/2008Pend Oreille Conservation DistrictMatch-$13,553.00
Spent12/09/2008Recreation and Conservation Office (RCO)Salmon State Projects-$76,797.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$90,350.00 $90,350.00 $90,350.00 $90,350.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
County:Pend Oreille
HUC12:Sweet Creek-Pend Oreille River (170102160902)
HUC8:Pend Oreille (17010216)
Lead Entity Area:Kalispel Tribe - Pend Oreille
Legislative District:07
Salmon Recovery Regions:Northeast Washington
Sections:14
Township:T38NR42E
Watershed Administrative Unit:Pend Oreille/Cedar Creek
WRIA:Pend Oreille
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.10mi0.10mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
7.50mi3.75mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
2.00
Square Miles Of streambed made accessible (C.2.b.2)
0.00sq mi
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
3.75mi
Number of bridges (C.2.g.2)
1.00
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
3.003.00
 Fishway chutes or pools installed (C.2.d.1)    
Number Of Fishway Chutes/Pools Installed (C.2.d.2)
1.00