DESCRIPTION
ELR Inc is the project
sponsor and the project type is a monitoring project. This request is to
support ongoing monitoring in the Asotin Creek Intensively Monitored Watershed
project (Asotin IMW). The project was started in 2008 and is expected to run
until 2019. The funds are being requested to support i) juvenile steelhead PIT
tagging and mark-recapture surveys, and ii)
habitat monitoring using the Columbia Habitat Monitoring protocol
(CHaMP). These two monitoring efforts are being used to assess the
effectiveness of large woody debris restoration at increasing juvenile
productivity in Asotin Creek. Three tributaries in Asotin Creek need to be
monitored: Charley Creek, North Fork Asotin Creek, and South Fork Asotin Creek.
The overall goal is to maintain the current level on monitoring and funds are
being requested because we have been informed that the current IMW monitoring
budget that is currently provided by Pacific State Marine Funding Commission
(PSMFC) may be reduced as of 2016 to between $0 and $100,000. It is critical at
this stage in the Asotin IMW to maintain the basic monitoring levels to ensure
that the goals of the IMW can be completed: namely to determine the
effectiveness of LWD restoration methods, determine the casual mechanisms of
habitat and fish responses, and to provide recommendations for implementing LWD
restoration in other watersheds. The extent of fish monitoring is 12 sites
300-500 m in length, 4 in each tributary (see attache
This project was an ongoing multi-year monitoring project to assess the effectiveness of stream restoration at increasing steelhead production. In 2017, we used these funds to conduct a complete round of habitat monitoring in Asotin Creek using the Columbia Habitat Monitoring Protocol (CHaMP) along with our other funding source (PSMFC). We completed 18 CHaMP sites from August-October 2017 and post-processed all the data. With the remaining monitoring funds we began analysis and summary of the CHaMP data to support a 10 year summary report for the IMW. The summary report will be completed in early 2018 and a copy will be provided to RCO.