Tucannon Large Wood & Floodplain Restoration PA6-9
#15-1323 #15-1323
Organization Snake River Salmon Recovery Board Lead Entity
Sponsor Department of Fish and Wildlife (WDFW)
Status Completed
Schedule Start Date: 12/9/2015 End Date: 5/20/2019
Category Category: Restoration
DESCRIPTION
WDFW will use the grant to restore large wood function to a 2 mile reach of the Tucannon River located on the W.T Wooten Wildlife Area (RM 45.8 RM 43.8). The Tucannon River, like most rivers, has been altered by human impacts, changing large reaches of the river from a pool and riffle type geometry, with diverse habitat, into a plane-bed form that lacks suitable habitat types. The proposed project is a process-based restoration intended to restore a pool and riffle bed-form, reconnect floodplain, and improve natural stream processes in the Tucannon River. The important role of large wood in Pacific N.W. streams is well documented. The project approach is to mimic historic conditions in the river based on reference reaches. The project will benefit native fish species including Spring Chinook, Steelhead, and Bull trout. A helicopter will be used to place the large wood structures. The use of helicopters is cost effective for reach scale projects reducing both impacts to the river and landscape and construction time. The project is part of a large scale restoration being done on the Tucannon River through BPA funding and was identified in both the Snake River Salmon Recovery Plan and the Tucannon River Geomorphic Assessment as a priority action. Conceptual designs for the project are complete, the next steps are to complete the design, develop staging areas for the large wood material, and acquire material for restoration. Project construction is scheduled for summer 2017.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/14/2015Department of Fish and Wildlife (WDFW)Match$100,000.00
Requested08/14/2015Recreation and Conservation Office (RCO)Salmon State Projects$400,000.00
Allocated05/20/2019Department of Fish and Wildlife (WDFW)Match$79,193.12
Allocated05/20/2019Recreation and Conservation Office (RCO)Salmon Federal Projects$316,772.49
Spent07/27/2018Department of Fish and Wildlife (WDFW)Match-$79,193.12
Spent07/27/2018Recreation and Conservation Office (RCO)Salmon Federal Projects-$316,772.49
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,201,000.00 $500,000.00 $395,965.61 $395,965.61 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Requested10/28/2016Bonneville Power Administration (BPA)Match$444,000.00
Allocated10/28/2016Bonneville Power Administration (BPA)Match$444,000.00
Spent10/28/2016Bonneville Power Administration (BPA)Match-$444,000.00
Other Funding Totals Proposed Requested Allocated Spent Balance
$0.00 $444,000.00 $444,000.00 $444,000.00 $0.00
Grand Totals Proposed Requested Allocated Spent Balance
$1,201,000.00 $944,000.00 $839,965.61 $839,965.61 $0.00
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Snake River Spring/Summer, Tucannon River, Threatened
County:Columbia
HUC12:Little Tucannon River-Tucannon River (170601070603)
HUC8:Lower Snake-Tucannon (17060107)
Lead Entity Area:Snake River
Legislative District:09
Salmon Recovery Regions:Snake River
Sections:03
Sections:15
Snake Major Spawning Areas:Upper Tucannon River
Steelhead-Pop (ESU):Steelhead-Snake River, Tucannon River, Threatened
Township:T09NR41E
Watershed Administrative Unit:Tucannon
WRIA:Middle Snake
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
2.00mi2.00mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
2.00mi2.00mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
10.00acres15.00acres
Instream Pools Created/Added (C.4.c.6)
10.000.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.11mi0.30mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
2.00mi2.00mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
4.80acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
2.00mi2.00mi
Number of structures placed in channel (C.4.d.7)
50.0054.00
Pools Created through channel structure placement (C.4.d.5)
25.0040.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
20.00yd