Yellowhawk Creek Dams
#99-1580 #99-1580
Organization Snake River Salmon Recovery Board Lead Entity
Sponsor Walla Walla County Conservation District
Status Completed
Schedule Start Date: 1/1/1999 End Date: 8/7/2002
Category Category: Restoration
Project Photo
DESCRIPTION
Yellowhawk Creek is the principle corridor for native Steelhead to reach the pristine spawning and rearing habitat of upper Mill and Blue creeks. The objective of this project is to remove the two primary fish passage barriers on the Yellowhawk, resulting in improved passage from the Walla Walla River to the protected headwaters of Mill Creek. This Steelhead run has been proposed for listing as threatened under the Endangered Species Act. These migratory fish cannot pass through the channelized, concrete portion of Mill Creek that flows through the city; therefore, they must utilize the Yellowhawk Creek corridor. This project will replace two concrete irrigation dams with five fish-passable v-log weirs and rootwads, and enhance a small section of riparian buffer. The removal of fish passage barriers has been recommended in several regional plans written for restoring salmon and steelhead in the the Walla Walla Basin. This project was ranked first in priority by a group of citizens and technical professionals within the watershed, including the Umatilla Tribes, Washington State Department of Fish and Wildlife, Walla Walla County, Cities, sportsmans' groups, local colleges, Department of Ecology, local irrigation districts, private landowners, and others. Project design will begin immediately, and will be installed by September 30, 1999.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested01/12/1999Recreation and Conservation Office (RCO)Salmon Federal Projects$55,000.00
Allocated08/07/2002Recreation and Conservation Office (RCO)Salmon Federal Projects$54,557.17
Spent08/07/2002Walla Walla County Conservation DistrictMatch-$0.00
Spent08/07/2002Recreation and Conservation Office (RCO)Salmon Federal Projects-$54,557.17
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$55,000.00 $55,000.00 $54,557.17 $54,557.17 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Middle Columbia River Spring, Not Warranted
City Areas:Walla Walla
County:Walla Walla
HUC12:Garrison Creek-Walla Walla River (170701020704)
HUC12:Russell Creek (170701020701)
HUC8:Walla Walla (17070102)
Lead Entity Area:Snake River
Legislative District:16
Salmon Recovery Regions:Snake River
Sections:28
Sections:29
Sections:33
Sections:37
Snake Major Spawning Areas:Middle Walla Walla River
Steelhead-Pop (ESU):Steelhead-Middle Columbia River, Walla Walla River, Threatened
Township:T06NR36E
Township:T07NR36E
Watershed Administrative Unit:Walla Walla Agricultural Lands
WRIA:Walla Walla
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.02mi0.02mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
4.00mi4.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
2.00
Square Miles Of streambed made accessible (C.2.b.2)
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
4.00mi4.00mi
Number of culverts (C.2.f.2)
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
2.002.00
 Fishway chutes or pools installed (C.2.d.1)    
Number Of Fishway Chutes/Pools Installed (C.2.d.2)
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.00mi0.00mi
Number of road-crossings (C.2.i.2)
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
Miles of Stream Treated for channel structure placement (C.4.d.3)
Number of structures placed in channel (C.4.d.7)
Pools Created through channel structure placement (C.4.d.5)
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)