| Organization | Snake River Salmon Recovery Board Lead Entity |
| Sponsor | Walla Walla County Conservation District |
| Status | Completed |
| Schedule | Start Date: 12/3/2014 End Date: 6/17/2016 |
| Category | Category: Restoration |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|---|---|---|---|---|
| Requested | 07/10/2014 | Walla Walla County Conservation District | Match | $23,009.00 | |
| Requested | 07/10/2014 | Recreation and Conservation Office (RCO) | Salmon State Projects | $130,380.00 | |
| Allocated | 06/17/2016 | Walla Walla County Conservation District | Match | $22,710.51 | |
| Allocated | 06/17/2016 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $128,688.63 | |
| Spent | 06/17/2016 | Walla Walla County Conservation District | Match | -$22,710.51 | |
| Spent | 06/17/2016 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | -$128,688.63 |
| Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
| $153,389.00 | $153,389.00 | $151,399.14 | $151,399.14 | $0.00 |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|
| Other Funding Totals | Requested | Allocated | Spent | Balance | |
| Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
| Chinook-Pop (ESU): | Chinook-Middle Columbia River Spring, Not Warranted |
| County: | Walla Walla |
| HUC12: | Lower Mill Creek (170701020204) |
| HUC8: | Walla Walla (17070102) |
| Lead Entity Area: | Snake River |
| Legislative District: | 16 |
| Salmon Recovery Regions: | Snake River |
| Sections: | 18 |
| Snake Major Spawning Areas: | Mill Creek-Walla Walla River |
| Steelhead-Pop (ESU): | Steelhead-Middle Columbia River, Walla Walla River, Threatened |
| Township: | T07NR37E |
| Watershed Administrative Unit: | Walla Walla Agricultural Lands |
| WRIA: | Walla Walla |
| APPLICATION | FINAL | ||||
| RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.18 | mi | 0.25 | mi | |
| Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 2.00 | mi | 2.00 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 2.00 | 2.00 | |||
Square Miles Of streambed made accessible (C.2.b.2) | 0.10 | sq mi | 0.10 | sq mi | |
| Fish passage blockages removed or altered (C.2.c.1) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | 2.00 | 2.00 | |||
| Fishway chutes or pools installed (C.2.d.1) | |||||
Number Of Fishway Chutes/Pools Installed (C.2.d.2) | 1.00 | 1.00 | |||
| Fish Screening Project | |||||
Quantity Of Water Protected By Screens (acre feet per year) (C.1.b) | 1,607.00 | acre-ft/yr | 1,607.00 | acre-ft/yr | |
| Fish screens installed (C.1.c.1) | |||||
Number Of Fish Screens Installed (C.1.c.2) | 1.00 | 1.00 | |||
The Flow Rate Of Screened Water (C.1.c.3) | 4.50 | cfs | 4.50 | cfs | |
| Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.18 | mi | 0.16 | mi | |
| Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | 0.20 | acres | 0.20 | acres | |
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.18 | mi | 0.16 | mi | |
Number of structures placed in channel (C.4.d.7) | 10.00 | 14.00 | |||
Pools Created through channel structure placement (C.4.d.5) | 10.00 | 10.00 | |||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | 10.00 | yd | 10.00 | yd | |
| Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 0.30 | acres | 0.30 | acres | |
*Total Riparian Miles Streambank Treated (C.5.b.1) | 0.50 | mi | 0.25 | mi | |
| Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | 0.30 | acres | 0.30 | acres | |
Miles of streambank planted (C.5.c.4) | 0.50 | mi | 0.50 | mi | |