DESCRIPTION
Project Area 40 is on the Tucannon Ranch located downstream of the Town of Starbuck in Columbia County. The Columbia Conservation district worked with the private landowner to set back river levees to the outside edge of the existing CREP easement boundary allowing for channel meander and inundation inside the levee set back. Two separate side channels were developed during the project with some excavation and LWD placement in the side channels. The completion of this project will improve winter rearing habitat for spring/summer and fall Snake River Chinook, summer steelhead and bull trout listed as threatened under ESA. This project will also improve spawning and rearing habitat for both fall Chinook and steelhead. Side channel and off channel refuge is limited in the main channel of the Tucannon and may be one of the leading factors limiting over winter survival of salmonids in the Tucannon. The project funding was through a RCO WDOE grant supported through the SRSRB Lead Entity (SRFB) with the objective of improving Fall Chinook spawning and rearing habitat in the lower river. In summary, the project removed 1,251 ft of river levee and opened 22.88 acre of low lying floodplain, and planted 1.69 acres with new riparian trees. Within the floodplain 0.45 miles of high flow side channel were augmented (increased access and wood added) and 0.22 miles of perennial side channel were created and treated with wood.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/01/2013Columbia Conservation DistrictMatch$89,638.00
Requested08/01/2013Recreation and Conservation Office (RCO)Salmon State Projects$461,860.00
Allocated04/01/2016Recreation and Conservation Office (RCO)Salmon State Projects$314,577.16
Spent04/01/2016Columbia Conservation DistrictMatch-$0.00
Spent04/01/2016Recreation and Conservation Office (RCO)Salmon State Projects-$314,577.16
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$551,498.00 $551,498.00 $314,577.16 $314,577.16 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Requested05/08/2013Department of Ecology (ECY)Match$461,860.00
Requested10/01/2013Bonneville Power Administration (BPA)Match$89,638.00
Allocated05/08/2013Department of Ecology (ECY)Match$264,000.00
Allocated10/01/2013Bonneville Power Administration (BPA)Match$55,000.00
Spent04/06/2015Bonneville Power Administration (BPA)Match-$55,000.00
Spent04/06/2015Department of Ecology (ECY)Match-$264,000.00
Other Funding Totals Proposed Requested Allocated Spent Balance
$0.00 $551,498.00 $319,000.00 $319,000.00 $0.00
Grand Totals Proposed Requested Allocated Spent Balance
$551,498.00 $1,102,996.00 $633,577.16 $633,577.16 $0.00
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Snake River Fall, Snake River Lower Mainstem, Threatened
Chinook2-Pop (ESU):Chinook-Snake River Spring/Summer, Tucannon River, Threatened
City Areas:Starbuck
County:Columbia
HUC12:Tucannon River (170601070704)
HUC8:Lower Snake-Tucannon (17060107)
Lead Entity Area:Snake River
Legislative District:09
Salmon Recovery Regions:Snake River
Sections:13
Sections:14
Snake Minor Spawning Areas:Lower Tucannon River
Steelhead-Pop (ESU):Steelhead-Snake River, Tucannon River, Threatened
Township:T12NR37E
Watershed Administrative Unit:Middle Snake Agricultural Lands
WRIA:Middle Snake
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.72mi0.60mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.72mi0.60mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
25.00acres25.00acres
Instream Pools Created/Added (C.4.c.6)
0.000.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.70mi0.62mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.72mi0.60mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
3.80acres0.90acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.70mi0.50mi
Number of structures placed in channel (C.4.d.7)
32.0033.00
Pools Created through channel structure placement (C.4.d.5)
32.0024.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
14.00yd5.00yd
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
2.00acres5.70acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.19mi0.24mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
2.00acres5.70acres
Miles of streambank planted (C.5.c.4)
0.19mi0.24mi
 Riparian Plant removal / control (C.5.h.1)    
Acres of riparian treated for plant removal/control (C.5.h.3)
3.70acres
Miles of streambank treated for plant removal/control (C.5.h.4)
0.24mi
ADDITIONAL INFORMATION