PA 24 Floodplain and Channel Complexity
#14-1900 #14-1900
Organization Snake River Salmon Recovery Board Lead Entity
Sponsor Columbia Conservation District
Status Completed
Schedule Start Date: 12/3/2014 End Date: 7/16/2018
Category Category: Restoration
Project Photo
DESCRIPTION
Project Area 24 (PA-24) is located within the active channel and floodplain of the Tucannon R. on private property, from the bridge at RM 28.25 to RM 27.5. PA-24 was identified as a tier 1 project in the Tucannon Conceptual Restoration Plan (Anchor 2011), identifying isolated habitats and low channel complexity compared to the goal >2 key LWD pieces (>6m long & 0.3m dia) (Salmon Recovery Plan for SE WA 2011). A preliminary design was prepared under SRFB grant (10-1831) and a final design was developed by the Tucannon Habitat Programmatic for implementation in 2015. A SRFB request for ~30% cost share to complete implementation was granted in 2015. The project was completed in August 2015 with the removal and breaching of 380' of river levee and the placement 498 key pieces LWD (>6m long & 0.3m dia) into 28 structures and 33 single log placement. The project created and enhanced 0.43 miles of side channel habitat and reconnected >5 ac of low floodplain. The project is expected to improve winter /summer rearing habitat for ESA listed Snake River spring Chinook, steelhead and winter rearing for Columbia bull trout.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/01/2014Columbia Conservation DistrictMatch$54,495.00
Requested08/01/2014Recreation and Conservation Office (RCO)Salmon State Projects$231,255.00
Allocated07/16/2018Columbia Conservation DistrictMatch$51,579.36
Allocated07/16/2018Recreation and Conservation Office (RCO)Salmon Federal Projects$218,882.18
Spent09/29/2015Recreation and Conservation Office (RCO)Salmon State Projects-$0.00
Spent07/16/2018Columbia Conservation DistrictMatch-$51,579.36
Spent07/16/2018Recreation and Conservation Office (RCO)Salmon Federal Projects-$218,882.18
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,003,771.00 $285,750.00 $270,461.54 $270,461.54 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Snake River Fall, Snake River Lower Mainstem, Threatened
Chinook2-Pop (ESU):Chinook-Snake River Spring/Summer, Tucannon River, Threatened
County:Columbia
HUC12:Town of Marengo-Tucannon River (170601070608)
HUC8:Lower Snake-Tucannon (17060107)
Lead Entity Area:Snake River
Legislative District:09
Salmon Recovery Regions:Snake River
Sections:13
Sections:18
Snake Major Spawning Areas:Upper Tucannon River
Steelhead-Pop (ESU):Steelhead-Snake River, Tucannon River, Threatened
Township:T11NR40E
Township:T11NR41E
Watershed Administrative Unit:Middle Snake Agricultural Lands
WRIA:Middle Snake
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.75mi0.75mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.75mi0.75mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
1.00acres5.00acres
Instream Pools Created/Added (C.4.c.6)
5.000.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.00mi0.32mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.75mi0.75mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
5.50acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.75mi0.75mi
Number of structures placed in channel (C.4.d.7)
21.0061.00
Pools Created through channel structure placement (C.4.d.5)
12.0026.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
20.00yd