DESCRIPTION
Pump Station Construction – 100% funded by WA Dept. of Ecology The pump station design work was done by WWCCD/WSCC engineers and technical personnel as Technical Assistance under the Irrigation Efficiency Program. The cost of construction was $323,000 which was provided by a single Conveyance Infrastructure grant from WA Department of Ecology (DOE). The following businesses and their employees contributed to construction of the Eastside/Westside pump station project which was
completed in 2006:
* Appellation LLC. provided construction management;
* Dunning Irrigation Supply was the primary contractor;
* Current Electric was the electrical subcontractor;
* Double T Construction was the subcontractor for concrete work.
Westside Pipeline Construction – This is a pressurized pipeline delivery system consisting of approximately 37,000 feet of pipeline which serves almost 1,200 acres of irrigated farmland. The project was 100% WA Dept. of Ecology funded. The Westside Pipeline design work was done by WWCCD/WSCC engineers and technical personnel as Technical Assistance under the Irrigation Efficiency Program. The total construction cost was $1,564,000 with $1,114,000 of that funded through WSCC administered Irrigation Efficiency Program and $450,000 provided through a WA Dept. of Ecology Conveyance Infrastructure grant. The following usinesses and their employees contributed to construction of the Westside pipeline project which was completed in 2008:
* Appellation LLC. provided construction management
* Premier Excavation was the primary contractor
* Dunning Irrigation Supply was the on-farm pump station subcontractor
* Current Electric was the electrical subcontractor.
Eastside Pipeline Construction – This is a pressurized pipeline delivery system consisting of approximately 35,500 feet of pipeline hich serves 800 acres of irrigatedfarmland. This phase was 100% WA Dept. of Ecology funded. As with the Westside project, the Eastside Pipeline design work was done by WWCCD/WSCC engineers andtechnical personnel as Technical Assistance under the Irrigation Efficiency Program. The total cost of the project was $1,208,000 with $888,000 funded through WSCC administered Irrigation Efficiency Program and $320,000 provided through WA Dept. of Ecology Conveyance Infrastructure grant. The following businesses and their employees contributed to construction of the Eastside pipeline project which was completed in 2009:
* Appellation LLC. provided construction management
* Premier Excavation was the primary contractor
* Dunning Irrigation Supply was the on-farm pump station subcontractor
* Current Electric was the electrical subcontractor.
Water Placed in Trust
3133.95 Ac-ft
1.853 cfs - March 15 - April 30
5.0 cfs - May 1 - June 30
1.853 cfs - July 1 - July 15
5.0 cfs - September 1 - September 15
9.0 cfs - September 16 - September 30
17.0 cfs - October 1 - October 15
22.0 cfs - October 16 - October 31
23.0 cfs - November 1 - November 15