Yakima River Side Channel at Bull Canal Diversion
#17-1179 #17-1179
 Upper Yakima Mainstem: Kittitas/Ellensburg/Thorp Reach Yakima River Side Channel at Bull Canal Diversion
Organization Yakima Basin Fish and Wildlife Recovery Board Lead Entity
Sponsor Mid-Columbia Fisheries Enhancement Group
Status Completed
Schedule Start Date: 1/19/2018 End Date: 3/17/2022
Category Category: Restoration
DESCRIPTION
In 1998, Washington Department of Fish and Wildlife installed a channel-spanning weir to direct flow into the 0.6 mile side channel at Yakima River Mile 153.5. From April 15 to late August, Bull Canal Company diverts up to 45cfs into an unscreened, 60-inch pipe located in the side channel 2,000 feet downstream of the river. When managed flow in the Yakima River is lowered in late August, the side channel dewaters, often very dramatically. Fish are stranded in the side channel and subject to increased predation. Bull Canal Company is unable to meet its irrigation needs from the side channel, and instead pulls its right (up to 30cfs) from Wilson Creek. The withdrawal of up to 30cfs from Wilson Creek exacerbates high water temperatures and poor habitat conditions in the stream. With the objectives of reducing fish mortality in the side channel, improving Wilson Creek late-season flow availability, and improving side channel habitat, MCFEG proposes to: 1) Remove the gated culverts and replace with a bridge or culvert, 2) Improve fish passage at the downstream end of the side channel, 3) Grade the side channel to increase conveyance and reduce stranding, 4) Remove the right side of the channel-spanning weir, 5) Repurpose the removed rocks by incorporating them into wood structures on the left bank, and 6) Excavate a new inlet and 420-ft length of side channel upstream of the existing inlet.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/01/2017Mid-Columbia Fisheries Enhancement GroupMatch$34,636.00
Requested08/01/2017Recreation and Conservation Office (RCO)Salmon State Projects$191,000.00
Allocated03/17/2022Mid-Columbia Fisheries Enhancement GroupMatch$28,874.78
Allocated03/17/2022Recreation and Conservation Office (RCO)Salmon Federal Projects$163,591.83
Spent01/20/2022Recreation and Conservation Office (RCO)Salmon State Projects-$0.00
Spent03/17/2022Mid-Columbia Fisheries Enhancement GroupMatch-$28,874.78
Spent03/17/2022Recreation and Conservation Office (RCO)Salmon Federal Projects-$163,591.83
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$225,636.00 $225,636.00 $192,466.61 $192,466.61 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
Chinook2-Pop (ESU):Chinook-Middle Columbia River Spring, Not Warranted
City Areas:Ellensburg
County:Kittitas
HUC12:Manastash Creek-Yakima River (170300010511)
HUC8:Upper Yakima (17030001)
Lead Entity Area:Yakima Basin
Legislative District:13
Salmon Recovery Regions:Middle Columbia River
Sections:03
Steelhead-Pop (ESU):Steelhead-Middle Columbia River, Yakima River Upper Mainstem, Threatened
Township:T17NR18E
Watershed Administrative Unit:Yakima River/Naneum Creek
WRIA:Upper Yakima
Yakima Subbasins:Ellensburg Reach - Yakima River Mainstem
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.61mi0.60mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.53mi0.60mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
1.10acres1.10acres
Instream Pools Created/Added (C.4.c.6)
0.000.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.60mi0.60mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.53mi0.60mi
 Channel structure placement (C.4.d.1)    
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.00mi
Number of structures placed in channel (C.4.d.7)
0.00
Pools Created through channel structure placement (C.4.d.5)
0.00
 Unspecified or other instream habitat project. (C.4.j.1)    
Unspecified Or Other Instream Habitat Project (C.4.j.2)
1.00mi