DESCRIPTION
BPA Contract 86023. The project was previously scheduled for construction to be completed in 2019, but was contingent on completion of the Barkley Irrigation Project in 2018 by another project sponsor. Delays in completion of the Barkley Irrigation Project continue to limit the scope of project implementation actions in 2020 to those actions which do not impact the Barkley Irrigation Company (BIC) infrastructure. With this limitation, MSRF has built a construction plan to implement Phase 1 actions in 2020. The remaining project elements are scheduled for implementation in Phase 2 in 2021, after BIC releases interests in the canal and headworks.
The goal of this Barkley Bear Phase 2 contract is to ensure that all work actions needed to complete materials acquisition, federal/state/local environmental permitting and reporting, construction, and site restoration can be completed prior to September 14, 2021. MSRF is working diligently to implement all required permitting activities for Phase 1 and Phase 2 of this project during the performance period of contract 83074 to the extent possible. Lastly, under this contracting action, MSRF will solicit and award contracts for project construction and revegetation/site restoration to be completed under this contract.
BPA Contract 86023. The project was
previously scheduled for construction to be completed in 2019, but was
contingent on completion of the Barkley Irrigation Project in 2018 by another
project sponsor. Delays in completion
of the Barkley Irrigation Project continue to limit the scope of project
implementation actions in 2020 to those actions which do not impact the
Barkley Irrigation Company (BIC) infrastructure. With this limitation, MSRF has built a
construction plan to implement Phase 1 actions in 2020. The remaining project elements are
scheduled for implementation in Phase 2 in 2021, after BIC releases interests
in the canal and headworks.
The goal of this Barkley Bear Phase 2 contract is to ensure that all work
actions needed to complete materials acquisition, federal/state/local
environmental permitting and reporting, construction, and site restoration
can be completed prior to September 14, 2021.
MSRF is working diligently to implement all required permitting
activities for Phase 1 and Phase 2 of this project during the performance
period of contract 83074 to the extent possible. Lastly, under this
contracting action, MSRF will solicit and award contracts for project
construction and revegetation/site restoration to be completed under this
contract.