Organization | Upper Columbia Salmon Recovery Board Lead Entity |
Sponsor | Methow Salmon Recovery Foundation |
Status | Active |
Schedule | Start Date: 12/29/2022 End Date: 12/7/2026 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 08/30/2022 | Methow Salmon Recovery Foundation | Match | $206,001.00 | |
Requested | 08/30/2022 | Recreation and Conservation Office (RCO) | Salmon State Supplemental Lg | $4,794,000.00 | |
Allocated | 12/22/2022 | Methow Salmon Recovery Foundation | Match | $206,001.00 | |
Allocated | 12/22/2022 | Recreation and Conservation Office (RCO) | Salmon State Supplemental Lg | $4,794,000.00 | |
Spent | 03/26/2025 | Methow Salmon Recovery Foundation | Match | -$2,138.34 | |
Spent | 03/26/2025 | Recreation and Conservation Office (RCO) | Salmon State Supplemental Lg | -$49,762.84 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$5,000,001.00 | $5,000,001.00 | $5,000,001.00 | $51,901.18 | $4,948,099.82 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Methow River, Endangered |
Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
County: | Okanogan |
HUC12: | Thompson Creek-Methow River (170200080605) |
HUC8: | Methow (17020008) |
Lead Entity Area: | Upper Columbia |
Legislative District: | 07 |
Salmon Recovery Regions: | Upper Columbia River |
Sections: | 06 |
Sections: | 07 |
Sections: | 30 |
Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Methow River, Threatened |
Township: | T33NR22E |
Township: | T34NR22E |
Upper Columbia Assesment Unit: | Methow River-Thompson Creek |
Watershed Administrative Unit: | Middle Methow River |
WRIA: | Methow |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 4.05 | mi | |||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 4.05 | mi | |||
Channel reconfiguration and connectivity (C.4.c.1) | |||||
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5) | 11.90 | acres | |||
Instream Pools Created/Added (C.4.c.6) | 0.00 | ||||
Miles of Off-Channel Stream Created or Connected (C.4.c.4) | 2.89 | mi | |||
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) | 2.58 | mi | |||
Channel structure placement (C.4.d.1) | |||||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 2.40 | mi | |||
Number of structures placed in channel (C.4.d.7) | 43.00 | ||||
Pools Created through channel structure placement (C.4.d.5) | 0.00 | ||||
Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.14 | mi | |||
Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 16.50 | acres | |||
*Total Riparian Miles Streambank Treated (C.5.b.1) | 1.77 | mi | |||
Debris/structures removal (C.5.j.1) | |||||
Acres of Riparian Area Treated. (C.5.j.2) | 0.10 | acres | |||
Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | 9.00 | acres | |||
Miles of streambank planted (C.5.c.4) | 1.33 | mi | |||
Wetland Project | |||||
Total Acres Of Wetland Area Treated (C.8.b) | 10.20 | acres | |||
Wetland improvement/ restoration (C.8.e.1) | |||||
Acres of wetland Improved/Restored (C.8.e.2) | 10.20 | acres |