Organization | Upper Columbia Salmon Recovery Board Lead Entity |
Sponsor | Yakama Nation |
Status | Completed |
Schedule | Start Date: 11/20/2015 End Date: 7/30/2017 |
Priority | 1 |
Category | Category: Restoration |
This project is a continuation of a project the Yakama Nation (YN) completed in 2012. The landowners at the time wanted to see how work that was completed in 2012 interacted with their respective properties prior to commencing with the work installed in 2017.
A total of three smaller cover structures were installed and an extension of an existing Engineered Log Structure (ELS) installed in 2012 referred to at structure #2. All structures are bank-based and keyed directly into the bank. No ferrous material was used in the 2017 installation unlike the cable used during 2012 installation. All logs for this installation were backfilled with native boulders and cobble. Fabric encapsulated soil lifts were installed along the face of each structure. Vertical snags were also installed using a vibrasonic implement for added stability and robustness.
All disturbed areas were planted with native vegetation upon project completion.
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Allocated | 07/30/2018 | Bonneville Power Admin | $130,000.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$130,000.00 | $0.00 | $130,000.00 | $0.00 | $130,000.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Entiat River, Endangered |
Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
County: | Chelan |
HUC12: | Preston Creek-Entiat River (170200100205) |
HUC8: | Upper Columbia-Entiat (17020010) |
Lead Entity Area: | Upper Columbia |
Legislative District: | 12 |
Salmon Recovery Regions: | Upper Columbia River |
Sections: | 28 |
Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Entiat River, Threatened |
Township: | T28NR19E |
Upper Columbia Assesment Unit: | Entiat River-Preston Creek |
Watershed Administrative Unit: | Middle Entiat |
WRIA: | Entiat |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.20 | mi | 0.20 | mi | |
Channel structure placement (C.4.d.1) | |||||
Number of structures placed in channel (C.4.d.7) | 3.00 | 3.00 |
![]() | Entiat 3D LWM Revisited stamped plans 06-07-2016.pdf |