M2 Reach WDFW Flow Connection
#BPA-P-77007 #BPA-P-77007
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Methow Salmon Recovery Foundation
Status Completed
Schedule Start Date: 9/25/2017 End Date: 9/24/2018
Category Category: Restoration
Project Photo
DESCRIPTION
BPA Contract 77007. The M2 WDFW Flow Connection project seeks to further enhance floodplain connection to peripheral side channel and wetland habitats by removing the final segment of a levee at the upstream edge of the M2 WDFW Floodplain Project area. The remaining segment is a cross levee that is perpendicular to the river channel and effectively blocks flow from a series of wetlands within an existing floodplain side channel during normal spring high flow periods.  MSRF removed the portion of the levee parallel to the river in 2013 as part of the larger project, but did not remove the cross levee due to adjoining landowner concerns. Following four years of post-project observations to demonstrate project benefits, the upstream landowner has agreed to allow removal of the levee. Removing the levee will reconnect a 3,200 foot-long wetland channel flowing through WDFW property and into adjacent protected wetland areas.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/25/2017Bonneville Power Administration (BPA)Upper Columbia Programmatic$78,828.00
Allocated09/25/2017Bonneville Power Administration (BPA)Upper Columbia Programmatic$78,828.00
Spent09/24/2018Bonneville Power Administration (BPA)Upper Columbia Programmatic-$59,160.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$78,828.00 $78,828.00 $78,828.00 $59,160.00 $19,668.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Requested04/26/2019US Bureau of ReclamationMatch$1,116.36
Allocated04/26/2019US Bureau of ReclamationMatch$1,116.36
Spent04/26/2019US Bureau of ReclamationMatch-$1,116.36
Other Funding Totals Proposed Requested Allocated Spent Balance
$0.00 $1,116.36 $1,116.36 $1,116.36 $0.00
Grand Totals Proposed Requested Allocated Spent Balance
$78,828.00 $79,944.36 $79,944.36 $60,276.36 $19,668.00
PRIMARY SPONSOR
PROJECT CONTACT
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Methow River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
County:Okanogan
HUC12:Thompson Creek-Methow River (170200080605)
HUC8:Methow (17020008)
Lead Entity Area:Upper Columbia
Legislative District:07
Salmon Recovery Regions:Upper Columbia River
Sections:25
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Methow River, Threatened
Township:T34NR21E
Upper Columbia Assesment Unit:Methow River-Thompson Creek
Watershed Administrative Unit:Middle Methow River
WRIA:Methow
View project on a larger map