CCNRD CMZ 20
#SRP-07-1735 #SRP-07-1735
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Chelan County Natural Resources Department
Status Completed
Schedule Start Date: 1/1/2007 End Date: 12/1/2010
Priority 1
Category Category: Restoration
Project Photo
DESCRIPTION
The Channel Migration Zone (CMZ) 20 project is located in an existing side channel of the Wenatchee River (RM 25) near Leavenworth. This project installed four large wood complexes. This project improves off-channel habitat for rearing and high flow refugia and it adds instream complexity for Chinook and steelhead.
Show more  ↓
FUNDING
Proposed Cost $169,932
Requested Funds $0
Allocated Funds $0
Spent Funds $0
Balance $0
FUNDING SOURCES
PROJECT CONTACT
SPONSOR
PHOTOS

 
LOCATION
Sections:12
Legislative District:12
County:Chelan
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Wenatchee River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
HUC12:Derby Canyon-Wenatchee River (170200110706)
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Wenatchee River, Threatened
Township:T24NR17E
Lead Entity Area:Upper Columbia
Salmon Recovery Regions:Upper Columbia River
WRIA:Wenatchee
HUC8:Wenatchee (17020011)
View project on a larger map
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Number of structures placed in channel 04 Number
Total Miles Of Instream Habitat Treated 00.08 Miles